INSP-Final Inspection | 2/12/2016 | 2/18/2016 | 2/18/2016 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Sprinkler Rough-in/Hydro | 2/16/2016 | 2/17/2016 | 2/17/2016 | A | PASS |
Troy Cobbley
|
|
|
Overhead hydro passed
|
INSP-Sprinkler Rough-in/Hydro | 2/16/2016 | 2/16/2016 | 2/16/2016 | P | PART |
Troy Cobbley
|
|
|
First floor hydro test passed. Second floor hydro test failed.
|
INSP-Sprinkler Rough-in/Hydro | 2/12/2016 | 2/16/2016 | 2/15/2016 | A | CANC |
Troy Cobbley
|
|
|
Matt is the contact. Thanks. Phone #: ###-#### >> Inspection requested via web by Stan Beus Inspection cancelled from web by: Stan Beus
|
INSP-Sprinkler Rough-in/Hydro | 1/26/2016 | 1/28/2016 | 1/28/2016 | A | FAIL |
Troy Cobbley
|
|
|
Overhead hydro failed due to cracked fitting at riser
|
INSP-Sprinkler Rough-in/Hydro | 1/25/2016 | 1/27/2016 | 1/27/2016 | A | CANC |
Troy Cobbley
|
|
|
Matt is the contact. Thanks. Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 12/8/2015 | 12/9/2015 | 12/9/2015 | P | PASS |
Troy Cobbley
|
|
|
Rough-in and tenting passed. Piping can be covered.
|
INSP-Sprinkler Rough-in/Hydro | 12/7/2015 | 12/7/2015 | 12/7/2015 | P | PASS |
Troy Cobbley
|
|
|
Rough-in passed. Need to provide additional bracing at the FDC. Can not cover until a tenting inspection has passed.
|