INSP-Final Inspection | 2/15/2016 | 2/17/2016 | 2/17/2016 | A | PASS |
Troy Cobbley
|
|
|
permit finaled
|
INSP-Sprinkler Rough-in/Hydro | 2/17/2016 | 2/17/2016 | 2/17/2016 | P | PASS |
Troy Cobbley
|
|
|
Overhead hydro passed
|
INSP-Sprinkler Rough-in/Hydro | 2/17/2016 | 2/17/2016 | 2/17/2016 | A | PASS |
Troy Cobbley
|
|
|
overhead hydro passed
|
INSP-Sprinkler Rough-in/Hydro | 2/12/2016 | 2/16/2016 | 2/16/2016 | A | FAIL |
Troy Cobbley
|
|
|
Overhead hydro test failed
|
INSP-Supply line flush | 2/15/2016 | 2/16/2016 | 2/16/2016 | A | PASS |
Troy Cobbley
|
|
|
underground flush passed
|
INSP-Sprinkler Rough-in/Hydro | 2/11/2016 | 2/11/2016 | 2/11/2016 | P | FAIL |
Troy Cobbley
|
|
|
Overhead hydro test failed
|
INSP-Sprinkler Rough-in/Hydro | 2/10/2016 | 2/11/2016 | 2/11/2016 | P | CANC |
Troy Cobbley
|
|
|
Phone #: ###-#### >> Inspection requested via web by Sam Ball Inspection cancelled from web by: Sam Ball
|
INSP-Supply line flush | 2/10/2016 | 2/11/2016 | 2/11/2016 | A | CANC |
Troy Cobbley
|
|
|
Phone #: ###-#### >> Inspection requested via web by Sam Ball Inspection cancelled from web by: Sam Ball
|
INSP-Sprinkler Rough-in | 12/3/2015 | 12/4/2015 | 12/4/2015 | A | PASS |
Troy Cobbley
|
|
|
Rough-in and tenting passed. Piping can be covered.
|
INSP-Sprinkler Rough-in | 11/25/2015 | 11/30/2015 | 11/30/2015 | A | PASS |
Troy Cobbley
|
|
|
Underground supply is ok to cover
|
INSP-Sprinkler Rough-in | 10/27/2015 | 10/28/2015 | 10/28/2015 | A | FAIL |
Troy Cobbley
|
|
|
Pipe is not at the minimum 4'-6" bury
|