INSP-Final Inspection | 10/25/2016 | 10/26/2016 | 10/26/2016 | A | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection passed/complete.
|
INSP-Sprinkler Rough-in | 7/27/2016 | 7/27/2016 | 7/27/2016 | P | PASS |
Jim Page
|
|
|
Tenting insulation inspection complete for overhead fire sprinkler piping located in attic spaces, overhead fire sprinkler piping approved for cover.
|
INSP-Sprinkler Rough-in/Hydro | 7/20/2016 | 7/20/2016 | 7/20/2016 | P | PASS |
Jim Page
|
|
|
Hydrostatic test for overhead fire sprinkler piping complete.
|
INSP-Sprinkler Rough-in | 7/20/2016 | 7/20/2016 | 7/20/2016 | P | PART |
Jim Page
|
|
|
Rough to cover inspection complete for overhead fire sprinkler piping, fire sprinkler piping not located in attic space approved for cover. Overhead fire sprinkler piping located in attic area's cannot be covered until tenting inspection has been completed.
|
INSP-Sprinkler Rough-in/Hydro | 6/22/2016 | 6/23/2016 | 6/23/2016 | A | PASS |
Jim Page
|
|
|
Level 2 hydrostatic test for overhead fire sprinkler piping complete.
|
INSP-Sprinkler Rough-in | 6/22/2016 | 6/23/2016 | 6/23/2016 | A | PASS |
Jim Page
|
|
|
Rough to cover inspection for overhead fire sprinkler piping on level 2 complete, level 2 overhead fire sprinkler piping approved for cover.
|
INSP-Sprinkler Rough-in | 5/20/2016 | 5/20/2016 | 5/20/2016 | P | PASS |
Jim Page
|
|
|
Rough to cover inspection for tenting of overhead fire sprinkler piping in attic space south of the firedoors complete, approved for cover. This inspection completes rough to cover inspections for this building, all piping approved for cover.
|
INSP-Sprinkler Rough-in | 4/28/2016 | 4/29/2016 | 4/29/2016 | P | PART |
Jim Page
|
|
|
200 psi hydrostatic test complete for level three, this completes the hydrostatic testing for this building. Rough in inspection complete for level 3, tenting insulation for overhead fire sprinkler piping, north of the fire doors complete. Hardlids north of the fire doors approved for cover. Remaining cover inspection for overhead fire sprinkler tenting south of the fire doors will be scheduled when insulation install is complete.
|
INSP-Sprinkler Rough-in/Hydro | 4/27/2016 | 4/28/2016 | 4/28/2016 | P | CANC |
Jim Page
|
|
|
Inspection request cancelled by point of contact on project, tenting insulation will not be complete by the time inspection can be done, inspection request will be rescheduled after insulation is complete
|
INSP-Sprinkler Rough-in | 4/13/2016 | 4/13/2016 | 4/13/2016 | P | PART |
Jim Page
|
|
|
2nd floor rough to cover complete, coordinated with point of contact placement for hanger adjustment. 2nd floor approved for cover.
|
INSP-Sprinkler Rough-in/Hydro | 4/13/2016 | 4/13/2016 | 4/13/2016 | P | PART |
Jim Page
|
|
|
2nd floor hydrostatic test complete.
|
INSP-Sprinkler Rough-in | 4/12/2016 | 4/12/2016 | 4/12/2016 | P | PART |
Jim Page
|
|
|
First floor rough to cover inspection complete, first floor approved for cover.
|
INSP-Sprinkler Rough-in/Hydro | 4/12/2016 | 4/12/2016 | 4/12/2016 | P | PART |
Jim Page
|
|
|
Hydrostatic test complete for first floor overhead fire sprinkler piping.
|