INSP-Final Inspection | 1/19/2017 | 1/19/2017 | 1/19/2017 | P | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection passed/complete
|
INSP-Supply line flush | 1/3/2017 | 1/3/2017 | 1/3/2017 | P | CANC |
Jim Page
|
|
|
Piping installed between underground to backflow was not the correct size, piping installed is 1 1/4 piping and the approved drawings shows an 1 1/2 supply, pipe replacement for correct size will be verified at final inspection.
|
INSP-Final Inspection | 12/29/2016 | 12/30/2016 | 12/30/2016 | P | CANC |
Jim Page
|
|
|
Final inspection for fire sprinklers will be rescheduled for a later date.
|
INSP-Supply line flush | 12/29/2016 | 12/30/2016 | 12/30/2016 | A | DONE |
Jim Page
|
|
|
Underground supply flush complete.
|
INSP-Supply line flush | 9/8/2016 | 9/9/2016 | 9/9/2016 | A | FAIL |
Jim Page
|
|
|
Flush will need to be performed again, something is obstructing the flow, piping will need to be repaired and flush rescheduled.
|
INSP-Sprinkler Rough-in | 8/25/2016 | 8/26/2016 | 8/26/2016 | A | PASS |
Jim Page
|
|
|
Rough to cover inspection for overhead fire sprinkler piping complete, overhead fire sprinkler piping approved for cover.
|
INSP-Supply line flush | 8/4/2016 | 8/5/2016 | 8/5/2016 | A | FAIL |
Jim Page
|
|
|
Could not verify if fire line is connected or not, flush could not be accomplished.
|
INSP-Sprinkler Rough-in/Hydro | 7/25/2016 | 7/25/2016 | 7/25/2016 | P | PASS |
Jim Page
|
|
|
Hydrostatic test for level 1 overhead fire sprinkler piping complete.
|
INSP-Sprinkler Rough-in | 7/20/2016 | 7/20/2016 | 7/20/2016 | P | PART |
Jim Page
|
|
|
Hydrostatic test complete for level 2 and level 3 overhead fire sprinkler piping. Overhead fire sprinkler piping on level 1 approved for cover. Overhead fire sprinkler piping that is between level 2 and level 3 living area's approved for cover. Fire sprinkler piping that is located between the roof deck & livings area's on level 2 and level 3 cannot be covered until a tenting inspection has been completed. Any piping in these area's that gets covered before tenting inspection is complete will have cover material removed to verify that tenting insulation has been installed..
|