Information based on query as of Wednesday, June 26, 2024.
Permit Information
Permit NumberFIR15-00905
StatusFinaled
Name SIMPLEX GRINNELL
Site Address 10118 W OVERLAND RD
Project NameRiver City Surgical Center
Customer Number 
ePlanReviewYes
Description
The fire sprinkler scope of work consists of providing protection in and existing building per NFPA 13. The attic is protected with attic sprinklers. The system utilizes above and below protection.

(RIVER CITY SURGICAL CENTER - BUILDING #1) Permit is to remodel an existing 2808 sq. ft. tenant space. Approval is contingent upon adhering to the approved plans on file. Work to include: removal of interior nonbearing walls leaving only the mechanical room walls in place, remove window and portion of exterior wall for new door at riser room and ADA Ramp, new construction of interior non-bearing walls to create (med gas room, two operating rooms, sterile room, janitors closet, compressor room, three ADA compliant restrooms, laundry room, locker room with ADA compliant roll in shower, break room, IT closet, two offices, riser room, reception/waiting area, storage room, four pre/post operation rooms, nurse’s station area and hallways), new ADA compliant exterior ramp, relocated front entry door, code compliant stoop with steps, electrical work, mechanical work, plumbing work and interior finishes in compliance with Ch. 8 of the 2012 IBC. Note: Med Gas room to have 1-hour fire barrier walls up to the underside of the roof deck. This building is fully Fire Sprinklered. Any alterations or modifications to the buildings Fire Sprinkler or Fire Alarm system WILL REQUIRE A SEPARATE PERMIT and shall be installed per NFPA 13 & NFPA 72 as regulated by the Boise Fire Department. **JG**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection5/3/20165/3/20165/3/2016PPASS
DetailsTroy Cobbley
Permit finaled
INSP-Final Inspection5/2/20165/2/20165/2/2016PFAIL
DetailsTroy Cobbley
Fire sprinkler interconnect with the FACP is finished. Need ceiling in the Gas Room and canopys on the pendant sprinkler heads for final.
INSP-Alarm Testing5/2/20165/2/20165/2/2016PDONE
DetailsTroy Cobbley
Fire sprinkler interconnect with the FACP is finished. Need ceiling in the Gas Room and canopys on the pendant sprinkler heads for final.
INSP-Sprinkler Rough-in/Hydro4/29/20164/29/20164/29/2016PCANC
DetailsTroy Cobbley
To be rescheduled for monday
INSP-Sprinkler Rough-in4/29/20164/29/20164/29/2016PCANC
DetailsTroy Cobbley
wrong entry made
INSP-Sprinkler Rough-in/Hydro4/28/20164/28/20164/28/2016PPASS
DetailsTroy Cobbley
Overhead hydro passed. Previous corrections have been addressed. Riser not finished yet (FDC) or alarm interconnections.
INSP-Sprinkler Rough-in/Hydro4/4/20164/4/20164/4/2016PPART
DetailsTroy Cobbley
Plan modifications are needed for these next items. Part of the rough-in is passed in the attic but one Attic Sprinkler is overspaced from a draftstop. Attice Heads have been installed in the overbuild leading to the front canopy. The lower sprinkler system has multiple addtional fittings and atleast on elevation change. Most of the changes noted were in the remote area on in the piping leading to the remote area. Overhead hydro canceled until changes and modifications have been approved and performed.
INSP-Sprinkler Rough-in/Hydro3/28/20163/28/20163/28/2016PPASS
DetailsTroy Cobbley
Underground hydro test passed
INSP-Supply line flush3/25/20163/25/20163/25/2016PPASS
DetailsTroy Cobbley
The underground flush passed. Steve and I discussed the height of the FDC. I quoted the 4' max height in NFPA 13
INSP-Supply line flush3/11/20163/14/20163/14/2016ACANC
DetailsTroy Cobbley
Please contact Steve Vaughn ###-#### for flush Phone #: ###-#### >> Inspection requested via web by Randy Knutson Inspection cancelled via mobile web on Monday, March 14, 2016.
INSP-Sprinkler Rough-in/Hydro3/10/20163/10/20163/10/2016PPASS
DetailsTroy Cobbley
Rough to cover inspection for underground piping passed. It was agreed that an additional 6" of cover above the level of the adjacent sidewalk will be provided to meet the 4'6" minimum bury depth.