INSP-Final Inspection | 5/3/2016 | 5/3/2016 | 5/3/2016 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Final Inspection | 5/2/2016 | 5/2/2016 | 5/2/2016 | P | FAIL |
Troy Cobbley
|
|
|
Fire sprinkler interconnect with the FACP is finished. Need ceiling in the Gas Room and canopys on the pendant sprinkler heads for final.
|
INSP-Alarm Testing | 5/2/2016 | 5/2/2016 | 5/2/2016 | P | DONE |
Troy Cobbley
|
|
|
Fire sprinkler interconnect with the FACP is finished. Need ceiling in the Gas Room and canopys on the pendant sprinkler heads for final.
|
INSP-Sprinkler Rough-in/Hydro | 4/29/2016 | 4/29/2016 | 4/29/2016 | P | CANC |
Troy Cobbley
|
|
|
To be rescheduled for monday
|
INSP-Sprinkler Rough-in | 4/29/2016 | 4/29/2016 | 4/29/2016 | P | CANC |
Troy Cobbley
|
|
|
wrong entry made
|
INSP-Sprinkler Rough-in/Hydro | 4/28/2016 | 4/28/2016 | 4/28/2016 | P | PASS |
Troy Cobbley
|
|
|
Overhead hydro passed. Previous corrections have been addressed. Riser not finished yet (FDC) or alarm interconnections.
|
INSP-Sprinkler Rough-in/Hydro | 4/4/2016 | 4/4/2016 | 4/4/2016 | P | PART |
Troy Cobbley
|
|
|
Plan modifications are needed for these next items. Part of the rough-in is passed in the attic but one Attic Sprinkler is overspaced from a draftstop. Attice Heads have been installed in the overbuild leading to the front canopy. The lower sprinkler system has multiple addtional fittings and atleast on elevation change. Most of the changes noted were in the remote area on in the piping leading to the remote area. Overhead hydro canceled until changes and modifications have been approved and performed.
|
INSP-Sprinkler Rough-in/Hydro | 3/28/2016 | 3/28/2016 | 3/28/2016 | P | PASS |
Troy Cobbley
|
|
|
Underground hydro test passed
|
INSP-Supply line flush | 3/25/2016 | 3/25/2016 | 3/25/2016 | P | PASS |
Troy Cobbley
|
|
|
The underground flush passed. Steve and I discussed the height of the FDC. I quoted the 4' max height in NFPA 13
|
INSP-Supply line flush | 3/11/2016 | 3/14/2016 | 3/14/2016 | A | CANC |
Troy Cobbley
|
|
|
Please contact Steve Vaughn ###-#### for flush Phone #: ###-#### >> Inspection requested via web by Randy Knutson Inspection cancelled via mobile web on Monday, March 14, 2016.
|
INSP-Sprinkler Rough-in/Hydro | 3/10/2016 | 3/10/2016 | 3/10/2016 | P | PASS |
Troy Cobbley
|
|
|
Rough to cover inspection for underground piping passed. It was agreed that an additional 6" of cover above the level of the adjacent sidewalk will be provided to meet the 4'6" minimum bury depth.
|