Permit Information
Permit NumberFIR16-00052
StatusFinaled
Name AMERICAN FIRE PROTECTION LLC
Site Address 3077 N CHRISTINE ST
Project NameIslamic Center
Customer Number 
ePlanReviewYes
Description
[Islamic Center]
The fire sprinkler scope of work consists of adding protection to an existing building due to a change of occupancy. The system is design as a grid type. The system is supply by new 6”x197’± C-900 piping with thrust blocks and fittings. The 2 ½” steel riser is supply by a 2 ½” backflow preventer. The piping is CPVC with above and below protection. The FDC is supplied at the end of primary cross main.

(ISLAMIC CENTER OF BOISE) The fire sprinkler system is used for fire area. To convert an existing 5,933 square foot office building to a place of religious worship. After the 515 square foot canopy addition is constructed, this building will have a total floor area of about 6,448 square feet. This building will have a fire sprinkler system and a fire alarm system installed in conjunction with this permit. Work is to include interior nonbearing walls, a new exterior door with sidelights, interior doors, interior windows, and finishes. Two restrooms will be upgraded to be accessible to the disabled. The canopy addition includes concrete footings, concrete piers, steel columns, steel beams, cold formed steel trusses, structural fiber cement board roof decking, and metal roofing. Special Inspection is required for soils, concrete, welding, bolts, and post installed concrete anchors. The design for the cold formed steel trusses is a deferred submittal item. The work is required to comply with the approved drawings, with the plan review report, and with all applicable codes and ordinances. The fire sprinkler system is required to comply with NFPA 13 and the fire alarm system is required to comply with NFPA 72 as regulated by the Fire Department. Separate fire sprinkler permits and fire alarm permits shall be obtained prior to beginning any installation work on such systems. **CJW**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection2/15/20172/17/20172/17/2017APASS
DetailsTroy Cobbley
Permit finaled
INSP-Final Inspection2/9/20172/10/20172/10/2017PFAIL
DetailsTroy Cobbley
All items have been corrected except dirt over the underground supply piping has not been addressed.
INSP-Sprinkler Rough-in12/7/201612/9/201612/9/2016PFAIL
DetailsJim Page
No fire sprinkler installed in riser room, heads need to be installed for room protection. No head box/extra heads in riser room, additonal cover for underground supply has not been added, additional soil needs to be added for proper cover as noted before. Fire sprinkler backflow does no have a current inspection tag, backlow needs to be tested and tagged by a licensed backflow tester. Fire sprinkler head next to heater unit in "Future Kitchen" area needs to be changed to a high temp head due to how close the head is to the ceiling mounted heater.
INSP-Final Inspection12/7/201612/9/201612/9/2016PCANC
DetailsJim Page
Inspection request is for a final, this request cancelled.
INSP-Supply line flush12/2/201612/5/201612/5/2016APASS
DetailsTroy Cobbley
Underground hydro test passed
INSP-Conference7/27/20167/28/20167/28/2016ADONE
DetailsTroy Cobbley
Draft stops for the upright sprinklers installed piping can be covered.
INSP-Sprinkler Rough-in/Hydro7/21/20167/22/20167/22/2016PPART
DetailsTroy Cobbley
For a cover inspection to be approved I need all of the draft stops installed per plan (one is missing entirely). Insulation in several locations is hanging down and blocking upright sprinkler head coverage. As per a previous request I need approved plans showing the extended coverage sidewalls in the northwest rooms. The overhead hydro test passed but the underground hydro test failed.
INSP-Supply line flush7/21/20167/22/20167/22/2016PFAIL
DetailsTroy Cobbley
The underground hydro test failed so no flush was performed.
INSP-Supply line flush7/20/20167/21/20167/21/2016PFAIL
DetailsTroy Cobbley
Arrived on site and found both the underground and overhead pressure guages way under 200psi. I spoke to Gordon and he is going to reschedule. No plans are on site for a rough-in for the draft stops.
INSP-Sprinkler Rough-in/Hydro7/20/20167/21/20167/21/2016PFAIL
DetailsTroy Cobbley
Arrived on site and found both the underground and overhead pressure guages way under 200psi. I spoke to Gordon and he is going to reschedule. No plans are on site for a rough-in for the draft stops.
INSP-Sprinkler Rough-in/Hydro7/7/20167/8/20167/8/2016ACANC
DetailsTroy Cobbley
Inspection was for an underground hydro but was not ready due to low pressure on the guage from a possible leak overnight
INSP-Supply line flush7/6/20167/7/20167/8/2016PCANC
DetailsTroy Cobbley
Rescheduled for tomorrow morning
INSP-Sprinkler Rough-in4/27/20164/28/20164/29/2016APART
DetailsTroy Cobbley
Thrust blocks are installed at the first 45's. All of the rest of the fittings are mechanically secured. The run of pipe from the 90 to the riser has been lowered 3" but is still 3" too high. I spoke to Jim Danes and he is going to follow up on whether they are going to lower the pipe or berm over it.
INSP-Supply line flush4/27/20164/27/20164/27/2016PPART
DetailsTroy Cobbley
The underground supply piping is ok to cover up to the first thrust block. Thrust blocks are being mixed by hand and were not done at the time of inspection. I noted that the piping from the 90 to the base of the riser is not at 4'-6" and will need to be buried deeper or landscaping performed to reach the required bury dept.

I also did a basic rough-in inspection on the overhead piping. For the most part everything is complete except for the riser build, eartquake bracing and draft stops required by the upright sprinkler heads. Plans need to be provided to plan review showing the additional fittings and elevation changes as well as the change of piping/heads in the rooms on the west side of the building where sidewalls are now being used. The said sidewalls are installed 3 1/2" below the ceiling so I will need verification they are listed for this.