INSP-Final Inspection | 12/30/2016 | 12/30/2016 | 12/30/2016 | A | PASS |
Jim Page
|
|
|
Final inspection for clean agent fire panel interface to existing fire alarm panel passed/complete, permit finaled.
|
INSP-Final Inspection | 4/19/2016 | 4/22/2016 | 4/22/2016 | A | PART |
Jim Page
|
|
|
Partial final inspection of clean agent alarm panel/clean agent release complete. All devices associated with clean agent fire alarms/tank activation tested, all devices that were tested passed inspection. Clean agent fire panel is not connected to the buildings main fire alarm system, clean agent fire panel needs to be monitored by the buildings main fire alarm panel (any modifications to the buildings fire alarm system will require a seperate FIR permit issued before work can be performed). A follow up inspection will need to be scheduled after interface between clean agent and main fire panel are complete. Once the panel interface is complete and inspected this FIR permit can be completed.
|
INSP-Final Inspection | 4/12/2016 | 4/19/2016 | 4/19/2016 | P | CANC |
Jim Page
|
|
|
Inspection request cancelled due to scheduling issue, inspection request will be rescheduled for a later date.
|