INSP-Final Inspection | 8/21/2017 | 8/22/2017 | 8/22/2017 | A | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection passed/complete
|
INSP-Final Inspection | 6/13/2017 | 6/15/2017 | 6/15/2017 | A | PART |
Jim Page
|
|
|
Partial final inspection for fire sprinklers complete. Main building as well as parking garages complete, town homes will have final inspection requested at a later date (General contractor is requesting TCO for main building untis and parking garage levels including lobbies on both 1st and 2nd, town homes to be completed at a later date)
|
INSP-Sprinkler Rough-in | 5/24/2017 | 5/31/2017 | 6/2/2017 | A | PASS |
Jim Page
|
|
|
Fire pump start up complete
|
INSP-Sprinkler Rough-in/Hydro | 6/1/2017 | 6/1/2017 | 6/1/2017 | P | PASS |
Jim Page
|
|
|
Hydrostatic test complete for entire building.
|
INSP-Sprinkler Rough-in/Hydro | 5/24/2017 | 5/26/2017 | 5/26/2017 | A | PASS |
Jim Page
|
|
|
Underground re-hydro tested due to developed leak from seperate contractor impacting thrust block. Restraints have been installed to protect underground from seperation due to site work and underground re-hydro complete.
|
INSP-Sprinkler Rough-in/Hydro | 5/17/2017 | 5/17/2017 | 5/17/2017 | P | PASS |
Jim Page
|
|
|
24 hour air test on both dry systems complete
|
INSP-Sprinkler Rough-in/Hydro | 5/16/2017 | 5/16/2017 | 5/16/2017 | P | PART |
Jim Page
|
|
|
24 hour air test on both dry systems started at 10:20AM with 49 PSI on both systems.
|
INSP-Sprinkler Rough-in/Hydro | 4/24/2017 | 4/24/2017 | 4/24/2017 | P | PART |
Jim Page
|
|
|
Hydrostatic test complete for garage dry systems (level 1 and 2 dry systems), stand pipe and overhead fire sprinkler piping in townhomes.
|
INSP-Sprinkler Rough-in | 4/11/2017 | 4/12/2017 | 4/12/2017 | A | PART |
Jim Page
|
|
|
Rough to cover inspection for overhead fire sprinkler piping in the outside soffit on northeast corner complete, approved for cover.
|
INSP-Sprinkler Rough-in | 3/28/2017 | 3/29/2017 | 3/29/2017 | A | PART |
Jim Page
|
|
|
Rough to cover inspection for fire sprinkler piping/pendant heads in lobby area complete, approved for cover.
|
INSP-Sprinkler Rough-in/Hydro | 3/28/2017 | 3/29/2017 | 3/28/2017 | P | CANC |
Jim Page
|
|
|
Hydro on town homes rough to cover on lobby. Phone #: ###-#### >> Inspection requested via web by Sam Ball Inspection cancelled from web by: Sam Ball
|
INSP-Sprinkler Rough-in | 2/10/2017 | 2/15/2017 | 2/15/2017 | A | PART |
Jim Page
|
|
|
Rough to cover inspection for west side cottages complete to include tenting for sprinkler piping in attic space, overhead fire sprinkler piping in cottages approved for cover.
|
INSP-Sprinkler Rough-in | 1/13/2017 | 1/13/2017 | 1/13/2017 | P | PART |
Jim Page
|
|
|
Rough to cover inspection for overhead fire sprinkler piping in the condo units on level 2 complete, approved for cover. Cottages on the west side still need to have rough to cover inspection performed before fire sprinkler piping can be covered.
|
INSP-Sprinkler Rough-in | 12/29/2016 | 12/30/2016 | 12/30/2016 | A | FAIL |
Jim Page
|
|
|
Overhead fire sprinkler piping on level 6 cannot be covered, every apartment on level 6 has piping that is completely covered with insulation, a clear pocket needs to be maintained between all overhead fire sprinkler piping and the sheetrock, tenting will need to be re-inspected
|
INSP-Sprinkler Rough-in | 12/20/2016 | 12/21/2016 | 12/21/2016 | P | DONE |
Jim Page
|
|
|
Request was for a conference, discussed tenting options with project superintendent to keep insulation on top of piping, also to maintain open space pocket between piping and vapor barrier/sheetrock for radiant heat to reach the piping.
|
INSP-Sprinkler Rough-in | 12/14/2016 | 12/15/2016 | 12/15/2016 | A | PART |
Jim Page
|
|
|
Soffit inspection for level 5 complete, soffit's approved for cover. Tenting will require modifications before cover will be approved.
|
INSP-Sprinkler Rough-in | 11/30/2016 | 11/30/2016 | 11/30/2016 | P | PASS |
Katie Marron
|
|
|
4th floor soffit/drops ok to cover.
Except first condo which was not ready.
Discussed soffit with cabinets and to treat the cabinet face as the 'wall', width is then 10" and no under soffit sprinklers required.
|
INSP-Sprinkler Rough-in | 11/8/2016 | 11/9/2016 | 11/9/2016 | P | PASS |
Katie Marron
|
|
|
Rough to cover on 6th floor. Dwelling units Ok to cover except connections to riser and trash shute loop.
Dry pendants were in but need to be adjusted so that deflectors are level.
From last inspection, Rm 302 requires additional sprinkler at upper ceiling. This was corrected ahead of time for the corrresponding room on the 6th floor.
|
INSP-Sprinkler Rough-in | 10/28/2016 | 10/31/2016 | 10/31/2016 | A | DONE |
Katie Marron
|
|
|
Third Floor Soffits inspected (except community space). - Soffit over 30' requires a sprinkler under in living room unit 304 -Unit 302 bedroom has sprinkler installed under soffit. Contractor to verify one is not required in ceiling pocket (ie meets exceptions of 8.10.8.2)
|
INSP-Sprinkler Rough-in | 10/7/2016 | 10/7/2016 | 10/7/2016 | P | PASS |
Jim Page
|
|
|
Rough to cover inspection for overhead fire sprinkler piping on level 5 complete, overhead fire sprinkler piping on level 5 approved for cover.
|
INSP-Sprinkler Rough-in | 9/19/2016 | 9/20/2016 | 9/20/2016 | A | PASS |
Jim Page
|
|
|
Rough to cover inspectio for overhead fire sprinkler piping on level 4 complete, overhead fire sprinkler piping on level 4 approved for cover. Informed job site superintendent to watch the insulation above metal channel, detail on fire sprinkler city approved drawings specifies how the insulation needs to be installed above the metal channel. Inspection for remaining overhead fire sprinkler piping located on level 3 complete, all overhead fire sprinkler piping located on level 3 approved for cover.
|
INSP-Supply line flush | 9/12/2016 | 9/13/2016 | 9/13/2016 | A | DONE |
Jim Page
|
|
|
Underground fire sprinkler main supply flush complete
|
INSP-Sprinkler Rough-in/Hydro | 9/9/2016 | 9/9/2016 | 9/9/2016 | A | PASS |
Jim Page
|
|
|
200 psi hydrostatic test complete for underground main supply.
|
INSP-Sprinkler Rough-in | 8/30/2016 | 9/1/2016 | 9/1/2016 | P | PART |
Jim Page
|
|
|
Partial rough to cover inspection complete for foverhead fire sprinkler piping located on levels 1, 2 and 3, notated city approved drawings with blue highlighter/red ink overhead fire sprinkler piping approved for cover.
|
INSP-Sprinkler Rough-in | 7/12/2016 | 7/12/2016 | 7/12/2016 | P | PASS |
Jim Page
|
|
|
Underground rough to cover inspection complete, underground approved for cover.
|