INSP-Final Inspection | 4/13/2017 | 4/17/2017 | 4/17/2017 | A | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection passed/complete
|
INSP-Final Inspection | 4/12/2017 | 4/14/2017 | 4/13/2017 | P | CANC |
Jim Page
|
|
|
Inspection scheduled for 17APR2017
|
INSP-Sprinkler Rough-in/Hydro | 3/21/2017 | 3/22/2017 | 3/22/2017 | A | PASS |
Jim Page
|
|
|
Rough to cover inspection for level 1 complete, approved for cover. Hydrostatic test for overhead fire sprinkler piping on level 1 complete.
|
INSP-Sprinkler Rough-in/Hydro | 2/7/2017 | 2/7/2017 | 2/7/2017 | P | PART |
Jim Page
|
|
|
Hydrostatic test complete for overhead fire sprinkler piping located on levels 2, 3, 4, and 5. Hydrostatic test complete for east and west standpipes (verified valves were in the open position before hydrostatic test time was started).
|
INSP-Sprinkler Rough-in | 1/24/2017 | 1/25/2017 | 1/24/2017 | A | PART |
Jim Page
|
|
|
Overhead fire sprinkler piping/pendant heads located above siffits/hardlids on level one appeoved for cover.
|
INSP-Sprinkler Rough-in | 1/18/2017 | 1/20/2017 | 1/20/2017 | A | PART |
Jim Page
|
|
|
Rough to cover inspection for overhead fire sprinkler piping located in elevator lobbies on levels 4 and 5 complete, approved for cover.
|
INSP-Sprinkler Rough-in | 1/3/2017 | 1/3/2017 | 1/3/2017 | P | PART |
Jim Page
|
|
|
Rough to cover inspection for sprinkler piping/sprinklers located in level 2 room entries complete, approved for cover.
|
INSP-Sprinkler Rough-in | 12/22/2016 | 12/22/2016 | 12/22/2016 | A | PART |
Jim Page
|
|
|
Rough to cover inspection for sprinkler piping/sprinklers located in level 3 room entries complete, approved for cover.
|
INSP-Sprinkler Rough-in/Hydro | 12/8/2016 | 12/9/2016 | 12/9/2016 | A | PART |
Jim Page
|
|
|
Rough to cover inspection for sprinkler piping/sprinklers located in level 4 room entries complete, approved for cover.
|
INSP-Sprinkler Rough-in | 11/11/2016 | 11/14/2016 | 11/14/2016 | A | PART |
Jim Page
|
|
|
Rough to cover inspection for overhead fire sprinkler piping located above drop down hardlids in level 5 rooms complete, overhead fire sprinkler piping located in drop down hardlids on level 5 approved for cover. Overhead fire sprinkler piping located in service rooms around level 4 elevator lobby approved for cover.
|
INSP-Sprinkler Rough-in | 11/7/2016 | 11/8/2016 | 11/8/2016 | P | CANC |
Troy Cobbley
|
|
|
Tyler Miller is the contact for this inspection. He needs a rough to cover inspection of 3 units on the 4th floor. Thank you Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 10/18/2016 | 10/19/2016 | 10/19/2016 | P | PASS |
Jim Page
|
|
|
Rough to cover inspection for overhead fire sprinkler piping/tenting located above northwest stairwell and northwest hotel room on level 5 complete, overhead fire sprinkler piping located in noted area's approved for cover.
|
INSP-Sprinkler Rough-in | 10/18/2016 | 10/18/2016 | 10/18/2016 | P | CANC |
Jim Page
|
|
|
Inspection request for 19OCT2016, this inspection request cancelled
|
INSP-Sprinkler Rough-in | 9/2/2016 | 9/6/2016 | 9/6/2016 | P | PASS |
Jim Page
|
|
|
Rough to cover inspection for level 5 including pipe tenting complete, all rooms on level 5 (excluding the room directly attached to the west stairwell, small amount of overhead fire sprinkler piping will be installed at a later date) approved for cover, spot checking will be performed at a later date to verify proper insulation coverage on fire sprinkler piping located in attic spaces.
|
INSP-Sprinkler Rough-in | 9/1/2016 | 9/1/2016 | 9/1/2016 | P | FAIL |
Jim Page
|
|
|
Fire sprinkler piping throughout multiple rooms had plastic sheeting (Tenting) removed exposing the pipe in the attic space, plastic sheeting will need to be repaired and re-inspected before cover can be approved for level 5.
|
INSP-Sprinkler Rough-in/Hydro | 8/24/2016 | 8/25/2016 | 8/25/2016 | A | FAIL |
Jim Page
|
|
|
Overhead fire sprinkler piping located in attic spaces on level 5 not approved for cover, plastic sheeting is installed over fire sprinkler piping but no insulation has been installed above piping, insulation tenting needs to installed over the fire sprinkler piping and inspected before cover of overhead fire sprinkler piping in attic spaces is approved.
|
INSP-Sprinkler Rough-in | 8/16/2016 | 8/19/2016 | 8/19/2016 | A | PART |
Jim Page
|
|
|
Rough to cover inspection for overhead fire sprinkler piping complete for rooms on levels 3, 4, and 5. Overhead fire sprinkler piping located in rooms on level 3 and 4 approved for cover, overhead fire sprinkler piping on level 5 needs to have tenting insulation installed and inspected before cover can be approved.
|
INSP-Sprinkler Rough-in | 6/10/2016 | 6/13/2016 | 6/13/2016 | A | PASS |
Jim Page
|
|
|
Rough to cover inspection complete for second floor rooms, notated city approved drawings with green highlighter/red ink for area's approved for cover.
|