INSP-Final Inspection | 2/28/2018 | 3/1/2018 | 3/1/2018 | A | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection complete.
|
INSP-Final Inspection | 2/15/2018 | 2/15/2018 | 2/15/2018 | P | PART |
Jim Page
|
|
|
Final fire sprinkler inspection for levels 3 and 4 complete.
|
INSP-Final Inspection | 2/5/2018 | 2/6/2018 | 2/6/2018 | A | PART |
Jim Page
|
|
|
Final fire sprinkler inspection for levels 5 and 6 complete.
|
INSP-Final Inspection | 1/15/2018 | 1/16/2018 | 1/16/2018 | A | PART |
Jim Page
|
|
|
Final fire sprinkler inspection for level 7 complete.
|
INSP-Sprinkler Rough-in | 12/11/2017 | 12/12/2017 | 12/12/2017 | A | PART |
Jim Page
|
|
|
Rough to cover inspection for live work area of first floor complete, approved for cover.
|
INSP-Sprinkler Rough-in/Hydro | 10/17/2017 | 10/18/2017 | 10/18/2017 | A | CANC |
Jim Page
|
|
|
We will have it pumped up around ten am Phone #: ###-#### >> Inspection requested via web by Sam Ball Inspection cancelled from web by: Sam Ball
|
INSP-Sprinkler Rough-in/Hydro | 9/18/2017 | 9/20/2017 | 9/20/2017 | A | PASS |
Jim Page
|
|
|
24 hour air test complete for levels 1 and 2 dry systems.
|
INSP-Sprinkler Rough-in | 9/20/2017 | 9/20/2017 | 9/20/2017 | A | PART |
Jim Page
|
|
|
Fire pump start up/commissioning complete. All tamper switches and flow switches in fire pump room complete. Final inspection for tampers and flows on level 1 and 2 wet systems complete.
|
INSP-Alarm Testing | 9/19/2017 | 9/20/2017 | 9/20/2017 | A | CANC |
Jim Page
|
|
|
Pump test at nine am. Phone #: ###-#### Inspection requested via web by Sam Ball
|
INSP-Sprinkler Rough-in/Hydro | 9/18/2017 | 9/19/2017 | 9/19/2017 | A | PART |
Jim Page
|
|
|
24 hour air test started at 0845 on 19SEPT2017, level 1 dry system at 43 psi, level 2 dry system at 42 psi
|
INSP-Sprinkler Rough-in/Hydro | 9/18/2017 | 9/20/2017 | 9/18/2017 | A | CANC |
Jim Page
|
|
|
Finish 24 hour air test on first floor dry system Phone #: ###-#### >> Inspection requested via web by Sam Ball Inspection cancelled from web by: Sam Ball
|
INSP-Sprinkler Rough-in/Hydro | 9/18/2017 | 9/19/2017 | 9/18/2017 | A | CANC |
Jim Page
|
|
|
24 hour air test Phone #: ###-#### >> Inspection requested via web by Sam Ball Inspection cancelled from web by: Sam Ball
|
INSP-Sprinkler Rough-in/Hydro | 9/14/2017 | 9/15/2017 | 9/15/2017 | A | PART |
Jim Page
|
|
|
Hydrostatic test for level 1 dry system complete
|
INSP-Alarm Testing | 9/13/2017 | 9/14/2017 | 9/14/2017 | A | PART |
Troy Cobbley
|
|
|
Could not test the fire alarm interconnections due to most of them not being shown on the fire alarm plans. Also appears flow switches and tamper switches have been deleted in the stairwells. What I was able to do today was trip test both of the dry systems. The first floor had water at the inspectors test in 49 seconds and the second floor was 32 seconds.
|
INSP-Sprinkler Rough-in/Hydro | 9/1/2017 | 9/5/2017 | 9/5/2017 | A | PART |
Jim Page
|
|
|
Rough to cover inspection for overhead fire sprinkler piping on level 2 wet system complete, level 2 wet system approved for cover. Hydrostatic test for level 1 and 2 wet systems complete. Hydrostatic test for level 2 dry system complete.
|
INSP-Sprinkler Rough-in/Hydro | 8/29/2017 | 8/30/2017 | 8/30/2017 | A | PASS |
Jim Page
|
|
|
Hydrostatic test for three standpipes complete.
|
INSP-Conference | 7/27/2017 | 7/27/2017 | 7/27/2017 | A | DONE |
Jim Page
|
|
|
Fire conference was for fire pump room access and egress, it is determined that the access to the fire pump room is adequate, no changes need to be made to current piping configuration on backflow preventer configuration. (Conference was with the Building Inspector Dave Hannah, Fire Inspector Supervisor Scott Arellano as well as installing contractor, Sam Ball)
|
INSP-Sprinkler Rough-in/Hydro | 4/25/2016 | 4/25/2016 | 4/25/2016 | P | PASS |
Jim Page
|
|
|
Underground hydrostatic test passed/complete
|