Permit Information
Permit NumberFIR16-00223
StatusFinaled
Name JBL FIRE PROTECTION LLC
Site Address 918 W IDAHO ST
Project NameAthlos Academies T.I.
Customer Number 
ePlanReviewYes
Description
[Athlos Academics TI]
The fire sprinkler scope of work consists of protecting an existing building with NFPA 13 system. The building will have two manual wet standpipes per NFPA 14. This building fire protection system has to be designed as Ordinary Hazard Group I due to a code alternative.

Plan Mod #1 – 10/25/2016
Added another cross main due to conflicts with HVAC

The standpipes and yard PIV are under permit FIR16-00158

(ATHLOS HEADQUARTERS – PHASE 3 – TENANT IMPROVEMENT) (DRH15-00410 AND DRH15-00444) The fire sprinkler system is used for building area increase, story increase, and for fire area. To remodel a 107,066 square foot existing building (23,570 square foot basement, 21,864 square foot 1st story, 7,272 square foot 1st story mezzanine, 944 square foot 1st story mechanical mezzanine, 22,242 square foot 2nd story, 23,095 square foot 3rd story, and 8,079 square foot 4th story) to be used for offices and as a training facility for a charter school. The seismic upgrade and other structural changes were done under permit BLD15-03621 (Phase 1). The streetscape, exterior wall finishes, shade awnings, canopies, windows, trellis, etc. were done under permit BLD16-00049 (Phase 2).
Basement: Work is to include an insulated 1-hr fire-resistance-rated ceiling, insulated interior nonbearing walls, a 1-hr stairway shaft enclosure, two parking spaces accessible to the disabled, and new openings in an existing interior concrete wall with steel angle headers and jambs to accommodate new louvers. Occupancies include an S-2 Occupancy parking garage (93 OL), a B Occupancy digital press room (3 OL), S-1 Occupancy storage rooms (4 OL), and mechanical rooms (7 OL).
1st story: Work is to include interior nonbearing walls, a Men’s shower/locker room with one shower accessible to the disabled, a Women’s shower/locker room with one shower accessible to the disabled, four multi-user toilet rooms, steps at the change of elevation at the alley, interior windows, interior doors, millwork, and interior finishes. An interior open stairway will be constructed from the 1st story to the 1st story mezzanine. Occupancies include an A-3 Occupancy sports field (103 OL), an A-3 Occupancy sports court (102 OL), an A-3 Occupancy break room (174 OL), a B Occupancy weight room (17 OL), an A-3 Occupancy lobby and circulation area (114 OL), S-1 Occupancy storage and mechanical rooms (3 OL), and B Occupancy locker rooms (14 OL).
1st story mezzanine: Work is to include a new 262 square foot floor system suspended from the floor above, a new open interior stairway to the 2nd story, glass guards, interior nonbearing walls, 2 multi-user restrooms accessible to the disabled, 1 single-user restroom accessible to the disabled, interior doors, interior windows, millwork, and finishes. Occupancies include a B Occupancy open office area (19 OL), B Occupancy classrooms (128 OL total), accessory I-4 Occupancy child care (20), B Occupancy massage room and IT room (3 OL), and S-1 Occupancy mechanical rooms (4 OL).
2nd story: Work is to include interior nonbearing walls, 2 multi-user restrooms accessible to the disabled, an interior set of steps and an interior ramp at the change of elevation at the pedestrian walkway that connects across the alley to a parking garage, interior doors, interior windows, glass guards, millwork, and finishes. Occupancies include B Occupancy offices (240 OL) and S-1 Occupancy mechanical rooms (1 OL).
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection4/27/20174/27/20174/27/2017PPASS
DetailsJim Page
Final fire sprinkler inspection passed/complete
INSP-Sprinkler Rough-in/Hydro4/26/20174/27/20174/27/2017PCANC
DetailsJim Page
Inspection request was for a final fire sprinkler inspection, this inspection request cancelled and a final inspection request will be generated.
INSP-Final Inspection3/21/20173/23/20173/23/2017APART
DetailsJim Page
Partial final inspection complete for fire sprinkler system. Fire pump commissioning is complete, dry system valve trip, low air and water flow for dry system testing complete, tamper switches and flow switches on all floors complete. Small amount of heads still need to be installed in miscellaneous spots where duct work/finish ceilings need to be installed, FIR permit will remain in issued status until remaining heads are installed and passed inspection.
INSP-Sprinkler Rough-in/Hydro3/23/20173/23/20173/23/2017APASS
DetailsJim Page
Hydrostatic testing for overhead fire sprinkler piping complete for entire scope of work.
INSP-Sprinkler Rough-in3/7/20173/7/20173/7/2017PPART
DetailsJim Page
Rough to cover inspection for fire sprinkler piping/pendant heads under stairs/stair landing on level 1 complete, approved for cover
INSP-Sprinkler Rough-in2/16/20172/17/20172/17/2017APART
DetailsJim Page
Rough to cover inspection for overhead fire sprinkler piping/installed pendant heads in suspended ceiling area's located on level 2, middle open section and rooms along the exterior walls to exlude the northside rooms (ceiling grid was not installed at time of inspection) complete, approved for cover.
INSP-Sprinkler Rough-in1/25/20171/26/20171/26/2017PPASS
DetailsJim Page
24hr air test for basement level dry system passed/compete
INSP-Sprinkler Rough-in1/24/20171/25/20171/25/2017ADONE
DetailsTroy Cobbley
24 hr test started at 1:00pm with 45psi on the guage.

I also spoke to the general contractor about the requirements for a sloped floor and floor drain in the fire pump room.
INSP-Sprinkler Rough-in1/11/20171/12/20171/12/2017APART
DetailsJim Page
Rough to cover inspection for overhead fire sprinkler located under the level 1 mezzanine, east side complete, approved for cover.
INSP-Sprinkler Rough-in1/3/20171/4/20171/4/2017ADONE
DetailsJim Page
Request was for a conference, discussed options for structural beams located on level 2.
INSP-Sprinkler Rough-in1/3/20171/3/20171/3/2017PPART
DetailsJim Page
Rough in inspection complete for overhead fire sprinkler piping below mezzanine on level one and basement level dry system.
INSP-Supply line flush12/21/201612/21/201612/21/2016PDONE
DetailsJim Page
Underground main line flush complete
INSP-Sprinkler Rough-in12/5/201612/5/201612/5/2016PPASS
DetailsJim Page
Underground hydro complete
INSP-Sprinkler Rough-in12/1/201612/2/201612/2/2016APASS
DetailsJim Page
Rough to cover inspection for underground complete, underground supply approved for cover.
INSP-Sprinkler Rough-in8/9/20168/10/20168/10/2016APART
DetailsJim Page
Partial rough to cover inspection completed for multiple floors, notated the city approved drawings with pink highlighter area's that rough to cover was completed on.