INSP-Final Inspection | 12/13/2016 | 12/13/2016 | 12/13/2016 | P | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection passed/complete
|
INSP-Alarm Testing | 12/13/2016 | 12/13/2016 | 12/13/2016 | P | CANC |
Jim Page
|
|
|
Inspection request is for a final inspection on fire sprinklers, this inspection request cancelled and a new one will be generated.
|
INSP-Final Inspection | 12/5/2016 | 12/6/2016 | 12/6/2016 | P | PART |
Jim Page
|
|
|
Partial final complete for overhead fire sprinkler system. Tampers and flow switches will be inspected during alarm inspection, heat chase was being installed for piping crossing the breezeway at time of this inspection. Chase heat for sprinkler piping will be verified during alarm/life safety inspection.
|
INSP-Sprinkler Rough-in | 8/1/2016 | 8/1/2016 | 8/1/2016 | P | PASS |
Jim Page
|
|
|
Tenting inspection for overhead fire sprinkler piping located in attic area's complete, overhead fire sprinkler piping located in attic spaces approved for cover. Only area's not approved for cover are where the fire sprinkler piping crosses the breeze-way, an approved method to prevent the pipe from freezing needs to be install/inspected before cover is approved. Any of the area's where the fire sprinkler piping crosses the breeze-way that gets covered before approved for cover will have any and all cover material removed for an inspection to be performed.
|
INSP-Sprinkler Rough-in | 7/25/2016 | 7/26/2016 | 7/26/2016 | A | FAIL |
Jim Page
|
|
|
Tenting insulation for overhead fire sprinkler piping located in attic spaces not installed, only plastic sheeting installed, noted in fire sprinkler review notes under general requirements, section 10: "A minimum of R38 of insulation is required on top of the piping per the IEC." Overhead fire sprinkler piping located in attic spaces not approved for cover.
|
INSP-Sprinkler Rough-in/Hydro | 7/19/2016 | 7/21/2016 | 7/21/2016 | A | PASS |
Jim Page
|
|
|
Hydrostatic test complete for levels 1, 2, 3 and 4 overhead fire sprinkler piping. Overhead fire sprinkler piping that is not in attic space is approved for cover, overhead fire sprinkler piping located in attic spaces cannot be covered until tenting insulation inspection is complete, overhead fire sprinkler piping that gets covered before tenting inspection is completed will have any and all cover removed for tenting inspection.
|
INSP-Supply line flush | 7/20/2016 | 7/21/2016 | 7/21/2016 | A | PASS |
Jim Page
|
|
|
Inspection request was for underground hydrostatic test and underground rough to cover, not a flush. Underground hydrostatic test passed/complete, underground supply approved for cover, flush will be completed at a later date.
|
INSP-Sprinkler Rough-in/Hydro | 7/7/2016 | 7/8/2016 | 7/8/2016 | P | PASS |
Jim Page
|
|
|
200 psi hydrostatic test complete for standpipe.
|