[The Fowler]
The fire sprinkler scope of work consists floors 3-7 above a podium. CPVC piping will be supplied from the previously installed standpipes using floor control valves. The entire building is protected per NFPA 13. The majority of the area uses residential sprinklers.

The previous review was for 1000 Gpm @ 100 Psi fire pump, three Class I automatic wet standpipes, two dry systems, two wet systems for podium 1st & 2nd floor levels. Some of the mains are required to be heat traced and insulated. There are retail areas on the first floor. Stair tower one has a combination standpipe with floor control valves. There is a horizontal exit with additional standpipe outlets.

Below the podium was reviewed under permit FIR16-00194
The underground was reviewed under permit FIR16-00116

Plan Mod #1 – 11/16/2016
The attic was filled with insulation. The owner has removed the insulation from the attic therefore the attic is required to be sprinklered. Concealed space sprinklers are being utilized with draft curtains.

(THE FOWLER - The East Building – On Top of podium) **GREEN TAG-Expedited Review-LEED Project - PROJECT MANAGEMENT-Angie Brosious**Permit to construct a new 88,615 square foot (5) story apartment building on top of the podium submitted under BLD15-02043. Each floor is approximately 17,723 square feet. Approval contingent upon adhering to the approved plans on file and attached engineering. This building is fully fire sprinklered with an NFPA 13 system to comply with the 5 story wood construction ordinance. Scope of work includes: construction of wood frame five story building, installation of interior non-bearing walls and bearing walls to create 109 individual units, new plumbing, new electrical, new mechanical, new insulation, new windows, new doors, and interior finishes in compliance with Chapter 8 of the 2012 IBC. This building will be sprinklered with a fully compliant NFPA 13 system to comply with the 5 story wood construction ordinance. **TLW**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection3/1/20183/1/20183/1/2018PPASS
DetailsJim Page
Final fire sprinkler inspection complete.
INSP-Final Inspection12/29/20171/2/20181/2/2018ACANC
DetailsJim Page
Inspection request cancelled per conversation with point of contact, Kevin Phone #: ###-####, inpsection will be rescheduled for a later date.
INSP-Sprinkler Rough-in/Hydro10/19/201710/19/201710/19/2017PPART
DetailsJim Page
Hydrostatic test for level 3 complete. Rough to ocver inspection for remaining pipe on level 3 complete, approved for cover.
INSP-Sprinkler Rough-in/Hydro10/4/201710/5/201710/5/2017APART
DetailsJim Page
Level 4 hydrostatic test complete. Rough to cover for overhead fire sprinkler piping associated with trash shoot on level 3 complete, approved for cover.
INSP-Sprinkler Rough-in/Hydro10/4/201710/5/201710/4/2017ACANC
DetailsJim Page
4th floor Phone #: ###-#### >> Inspection requested via web by Sam Ball Inspection cancelled from web by: Sam Ball
INSP-Sprinkler Rough-in/Hydro9/20/20179/21/20179/21/2017APART
DetailsJim Page
Hydrostatic test for overhead fire sprinkler piping on level 5 complete.
INSP-Sprinkler Rough-in9/19/20179/20/20179/20/2017APART
DetailsJim Page
Rough to cover inspection for trash shoots on levels 5 and 7 complete, approved for cover. Inspection for remaining overhead fire sprinkler piping on level 5 complete, level 5 approved for cover.
INSP-Sprinkler Rough-in/Hydro9/18/20179/19/20179/20/2017APART
DetailsJim Page
Rough to cover inspection for level 6 complete, level 6 approved for cover. Hydrostatic test for all of level 6 complete.
INSP-Sprinkler Rough-in/Hydro9/8/20179/11/20179/11/2017APART
DetailsJim Page
Fire pump start up complete, due to the length and amount of fire hose required to prevent erosion from the fire pump test the gallons per minute could not be reached (approximatly 700 feet of fire hose was required to be used due to road removal on the east side of building by the fire pump room, heavy equipment operations and no close place for water containment without severe soil wash-out issues near the building.). Fire pump flow test will be completed on another day.
INSP-Sprinkler Rough-in/Hydro9/8/20179/11/20179/11/2017APART
DetailsJim Page
Hydrostatic test for overhead fire sprinkler piping on level 7 complete.
INSP-Sprinkler Rough-in/Hydro8/29/20178/30/20178/30/2017APART
DetailsJim Page
Hydrostatic test for overhead fire sprinkler piping located on level 6 A side (East of fire doors) complete.
INSP-Sprinkler Rough-in/Hydro8/29/20178/29/20178/29/2017PDONE
DetailsJim Page
Rough to cover inspection for remaining overhead fire sprinkler piping/pendant heads on A side level 6 complete, approved for cover.
INSP-Sprinkler Rough-in/Hydro8/29/20178/29/20178/29/2017PCANC
DetailsJim Page
Phone #: ###-#### >> Inspection requested via web by Sam Ball Inspection cancelled from web by: Sam Ball
INSP-Sprinkler Rough-in6/13/20176/13/20176/13/2017PPART
DetailsJim Page
Rough to cover inspection for overhead fire sprinkler piping located above hardlids in the B side 7th floor complete (west wing) hardlids approved for cover.
INSP-Sprinkler Rough-in6/1/20176/1/20176/1/2017PPART
DetailsJim Page
Rough to cover inspection for overhead fire sprinkler piping on level 7 A wing (east wing) complete, approved for cover.
INSP-Sprinkler Rough-in5/15/20175/17/20175/17/2017APART
DetailsJim Page
Rough to cover inspection for overhead fire sprinkler piping located above hardlids in the B side 3rd-6th floors complete (west wing) hardlids approved for cover.
INSP-Sprinkler Rough-in5/10/20175/10/20175/10/2017PPART
DetailsJim Page
Rough to cover inspection for overhead fire sprinkler piping located above hardlids on east wing complete, levels 3, 4, 5 and 6, all hardlids on noted levels for east wing approved for cover.
INSP-Conference3/2/20173/2/20173/2/2017ADONE
DetailsJim Page
Temporary standpipe is in place, located on the south side (Myrtle is the access street for FDC connection) of building.