INSP-Final Inspection | 3/7/2017 | 3/7/2017 | 3/7/2017 | P | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection passed/complete
|
INSP-Final Inspection | 10/20/2016 | 10/20/2016 | 10/20/2016 | P | PART |
Jim Page
|
|
|
Final fire sprinkler inspection for level 6 and 7 complete. FIR permit will stay in issued status (Partial final for records) until BLD permit is ready to be finaled on life fire safety, at time of life fire safety completion FIR permit will be finaled as well.
|
INSP-Sprinkler Rough-in | 7/20/2016 | 7/21/2016 | 7/21/2016 | P | PASS |
Jim Page
|
|
|
Rough to cover inspection for overhead fire sprinkler piping on level 7 complete, overhead fire sprinkler piping located on level 7 approved for cover.
|
INSP-Sprinkler Rough-in/Hydro | 7/20/2016 | 7/21/2016 | 7/21/2016 | A | PASS |
Jim Page
|
|
|
Hydrostatic test complete for overhead fire sprinkler piping located on level 7.
|
INSP-Sprinkler Rough-in/Hydro | 7/12/2016 | 7/13/2016 | 7/13/2016 | P | DONE |
Jim Page
|
|
|
Rough to cover inspection for overhead fire sprinklers complete for level 6 as well as overhead fire sprinkler hydrostatic test for level 6.
|
INSP-Sprinkler Rough-in/Hydro | 7/11/2016 | 7/11/2016 | 7/11/2016 | P | PASS |
Jim Page
|
|
|
Hydrostatic test complete for level 6
|
INSP-Sprinkler Rough-in/Hydro | 7/6/2016 | 7/7/2016 | 7/7/2016 | A | PASS |
Jim Page
|
|
|
Rough to cover inspection for overhead fire sprinkler piping complete for level 6, level 6 overhead fire sprinkler piping approved for cover.
|