Information based on query as of Wednesday, June 26, 2024.
Permit Information
Permit NumberFIR16-00280
StatusFinaled
Name STATEFIRE DC SPECIALTIES
Site Address 1401 S ROBERT ST
Project NameWells Fargo Basement Lobby
Customer Number 
ePlanReviewYes
Description
[Wells Fargo Boise Center] - Quick Permit
Relocate sprinkler obstructed by new duct enclosure

(WELLS FARGO BOISE CENTER) Plan Modification 2 – at the basement area select nonbearing walls to create a IDE room, new ductless ac system in IDE room, relocate light fixture, some electrical work and refinish the training room area. JG 4-14-16 // Plan Modification 1 - walls near elevator lobby on 1st floor revised to 1-hour corridor rating, smoke dampers required on ducts penetrating shaft wall at corridor, enclosing shaft with 1-hour rating in basement, at shaft fire dampers required where duct penetrates basement rated wall and where ducts passes 1st floor ceiling. JG 3-28-16// Permit To remodel 582 sq. ft. of an existing bank service center office entry space on the main floor in an existing building with two stories and a basement. Approval is contingent upon adhering to the approved plans on file. Work is to include: removal of select; interior brick wall, select wall, exterior storefront door and glazing, entry column, acoustic ceiling and elevator smoke doors, construction of new select; interior nonbearing walls, storefront double doors, storefront windows, acoustic ceiling, entry columns, above entry cornice, light fixtures, electrical work, mechanical duct work and interior finishes in compliance with Ch. 8 of the 2012 IBC. NOTE: This building is fire sprinklered in the basement only. **JG**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection6/21/20166/22/20166/22/2016APASS
DetailsJim Page
Final fire sprinkler inspection passed/complete
INSP-Final Inspection6/15/20166/16/20166/16/2016ACANC
DetailsTroy Cobbley
Scheduled with our alarm final. Mike Kroll Will be point of contact.(###-####) Phone #: ###-#### Inspection requested via web by Randy Knutson
INSP-Sprinkler Rough-in4/26/20164/27/20164/27/2016APASS
DetailsJim Page
Rough to cover inspection complete for sprinkler modifications in elevator lobby, basement level, overhead fire sprinkler piping in elevator lobby approved for cover.