Information based on query as of Wednesday, June 26, 2024.
Permit Information
Permit NumberFIR16-00299
StatusFinaled
Name PHOENIX FIRE PROTECTION
Site Address 400 S CAPITOL BLVD
Project NameResidence Inn Wet Parking
Customer Number 
ePlanReviewYes
Description
[Residence Inn - Floors 3-10, Partial 1st]
The fire sprinkler scope of work consists of partial first floor and floors 3-10. Each floor has floor control valves. The system is designed per NFPA 13. There is a 750 Gpm @ 120 Psi fire pump.

The underground piping is under permit FIR16-00040
The fire pump is under permit FIR16-00090
The standpipes are under permit FIR16-00231
The parking garage is under FIR16-00285

(RESIDENCE INN BY MARRIOTT) Permit to construct a new 204,396 square foot hotel / restaurant / assembly high-rise building. PLAN MODIFICATION 4-7-16 - Modification submitted to change cast iron plumbing to ABS plumbing. **TLW** This building consists of 8 stories of residential hotel above two stories of parking garage / restaurant. A foundation permit was issued for this project under BLD15-02707. Work to include: construction of new rated concrete building, new plumbing, new electrical, new mechanical, new fire sprinklers, new shafts, new interior partitions, and interior finishes in compliance with chapter 8 of the 2012 IBC. This building is to be fully fire sprinklered with an NFPA 13 system and fully alarmed with a NFPA 72 system. **TLW**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection1/16/20181/17/20181/17/2018PPASS
DetailsJim Page
Final fire sprinkler inspection for area of work complete.
INSP-Final Inspection10/9/201710/9/201710/9/2017APART
DetailsJim Page
Final fire sprinkler inspection complete, permit will remain in issued status until completion of the project.
INSP-Sprinkler Rough-in/Hydro9/26/20179/27/20179/27/2017PPASS
DetailsJim Page
Hydrostatic test for level 8 complete
INSP-Sprinkler Rough-in/Hydro9/27/20179/27/20179/27/2017APART
DetailsJim Page
Hydrostatic test for level 1 wet system complete
INSP-Final Inspection9/26/20179/27/20179/27/2017ACANC
DetailsJim Page
Inspection for level 1 hydro, final inspection to be completed at a later date, this request is cancelled.
INSP-Sprinkler Rough-in/Hydro9/26/20179/27/20179/26/2017ACANC
DetailsJim Page
Contact Ken Orahood ###-#### 30 min prior to Fire Final Insp start please
Final 1st floor Wet system
Hydro 1st floor Wet system sched for Afternoon
Thank YOU
Phone #: ###-#### >> Inspection requested via web by Teri Cruickshank Inspection cancelled from web by: Teri Cruickshank
INSP-Sprinkler Rough-in/Hydro9/22/20179/25/20179/25/2017PPART
DetailsJim Page
Hydrostatic test for overhead fire sprinkler piping complete for level 9 and 10.
INSP-Sprinkler Rough-in/Hydro9/18/20179/19/20179/19/2017ACANC
DetailsJim Page
Inspection request was for fire pump start up, fire pump is under FIR16-00090, this request is cancelled.
INSP-Sprinkler Rough-in8/4/20178/7/20178/7/2017APART
DetailsJim Page
Rough to cover inspection for overhead fire sprinkler piping/pendant heads complete for 3rd floor corridor as well as 4th floor 02 room, inspected area's approved for cover.
INSP-Sprinkler Rough-in8/1/20178/1/20178/1/2017PPART
DetailsJim Page
Rough to cover inspection for overhead fire sprinkler piping/pendant heads in floors 5,6,7 ; 8 number 02 bedrooms complete (Rooms that were completed after construction elevator was removed) approved for cover.
INSP-Conference7/13/20177/14/20177/14/2017ADONE
DetailsJim Page
Fire conference complete
INSP-Sprinkler Rough-in7/3/20177/6/20177/6/2017APART
DetailsJim Page
Rough to cover inspection for overhead fire sprinkler piping/pendant heads for the Laundry Chute, 10th floor conference room complete, approved for cover. Inspection request was also for fire pump commissioning, I stopped the fire pump commissioning, no water was flowed due to erosion issues (no curbing, loose dirt that would have been washed out, nearest storm drain was downstream from a dirt pile)
INSP-Sprinkler Rough-in6/22/20176/23/20176/23/2017APART
DetailsJim Page
Rough to cover inspection for overhead fire sprinkler piping/pendant heads located in the corridors on 4th-8th floors complete, approved for cover, pool area and rooms attached to pool area approved for cover.
INSP-Sprinkler Rough-in6/22/20176/22/20176/22/2017PCANC
DetailsJim Page
Inspection request rescheduled for 23JUNE2017
INSP-Sprinkler Rough-in6/22/20176/22/20176/22/2017PCANC
DetailsJim Page
3rd Floor pool arePls call 30 mins prior Phone #: ###-#### >> Inspection requested via web by Teri Cruickshank Inspection cancelled from web by: Teri Cruickshank
INSP-Conference6/8/20176/12/20176/12/2017ADONE
DetailsJim Page
Fire conference complete, current configuration of fire sprinkler heads in studio A apartment rooms is adequate, no changes necessary.
INSP-Sprinkler Rough-in5/23/20175/24/20175/24/2017APART
DetailsJim Page
Rough to cover inspection for overhead fire sprinkler piping/pendant heads on the northwest side level 3 conference room, corridors and restrooms complete, approved for cover.
INSP-Sprinkler Rough-in5/16/20175/17/20175/17/2017APART
DetailsJim Page
Rough to cover inspection for overhead fire sprinkler piping/pendant heads in hotel resident rooms on level 10 complete, hotel resident rooms on level 10 approved for cover.
INSP-Sprinkler Rough-in4/27/20175/1/20175/1/2017PPART
DetailsJim Page
Rough to cover inspection for overhead fire sprinkler piping/pendant heads located in level 1 lobby complete, approved for cover.
INSP-Sprinkler Rough-in4/25/20174/26/20174/26/2017APART
DetailsJim Page
Rough to cover inspection for overhead fire sprinkler piping/pendant heads in hotel resident rooms on level 9 complete, hotel resident rooms on level 9 approved for cover.
INSP-Sprinkler Rough-in/Hydro4/7/20174/10/20174/10/2017APART
DetailsJim Page
Rough to cover inspection for overhead fire sprinkler piping/pendant heads in hotel resident rooms on level 8 complete, hotel resident rooms on level 8 approved for cover. Rough in inspection complete for level 9, rough to cover inspection will be scheduled when pendant heads are installed.
INSP-Sprinkler Rough-in/Hydro3/30/20174/3/20174/3/2017PPART
DetailsJim Page
Rough to cover inspection for overhead fire sprinkler piping/pendant heads in hotel resident rooms on level 7 complete, hotel resident rooms on level 7 approved for cover. Hydrostatic test complete for supply from pump room to floor control valves complete as well as overhead fire sprinkler piping on levels 3, 5, 6 and 7.
INSP-Sprinkler Rough-in/Hydro3/29/20173/30/20173/30/2017ACANC
DetailsJim Page
Contact will be Ken Orahood - Needing Hydro inspections for 3rd, 5th, 6th, 7th floors, RTC for 7th floor and Hydro for 8" & 6" Mains....
Questions please let us know... Thanks
Phone #: ###-#### >> Inspection requested via web by Teri Cruickshank Inspection cancelled from web by: Teri Cruickshank
INSP-Sprinkler Rough-in3/14/20173/16/20173/16/2017APART
DetailsJim Page
Rough in inspection for overhead fire sprinkler piping on level 8 complete. Rough to cover inspection for overhead fire sprinkler piping/pendant heads in hotel tenant rooms on level 6 complete, hotel tenant rooms approved for cover.
INSP-Sprinkler Rough-in3/14/20173/16/20173/14/2017ACANC
DetailsJim Page
Inspection is for the 6th Floor
Contact is Ken Orahood ###-#### Phone #: ###-#### >> Inspection requested via web by Teri Cruickshank Inspection cancelled from web by: Teri Cruickshank
INSP-Sprinkler Rough-in3/1/20173/2/20173/2/2017APART
DetailsJim Page
Rough to cover inspection for overhead fire sprinkler piping/pendant heads in hotel resident rooms on level 5 complete, hotel resident rooms on level 5 approved for cover.
INSP-Conference3/2/20173/2/20173/2/2017ADONE
DetailsJim Page
Temporary standpipe for fire department use partially complete, contractor has hose valves on order, when valves are recieved they will installed with the FDC hookup.
INSP-Sprinkler Rough-in/Hydro3/1/20173/2/20173/2/2017APART
DetailsJim Page
Hydrostatic test for the level 4 complete.
INSP-Sprinkler Rough-in2/22/20172/24/20172/24/2017APART
DetailsJim Page
Rough to cover inspection for overhead fire sprinkler piping/pendant heads in hotel rooms on level 3 complete (public common area's will need inspected after pendant heads are installed at a later date). Hotel rooms approved for cover on level 3.
INSP-Sprinkler Rough-in2/16/20172/17/20172/17/2017APASS
DetailsJim Page
Rough to cover inspection for overhead fire sprinkler piping/pendant heads in hotel rooms on level 4 complete, hotel rooms on level 4 approved for cover.
INSP-Sprinkler Rough-in2/16/20172/21/20172/16/2017ACANC
DetailsJim Page
Contact will be Ken Orahood please contact him 30 minutes before Inspection Phone #: ###-#### >> Inspection requested via web by Teri Cruickshank Inspection cancelled from web by: Teri Cruickshank
INSP-Sprinkler Rough-in2/1/20172/3/20172/3/2017APART
DetailsJim Page
Rough in inspection complete for levels 6 and 7, a rough to cover inspection will need to be performed after finish heads are cut before cover can be approved.
INSP-Sprinkler Rough-in12/8/201612/9/201612/9/2016APART
DetailsJim Page
Rough in inspection complete for installed overhead fire sprinkler piping (wet systems only) complete for levels 1, 3, 4 and 5. A rough to cover inspection will need to be completed before cover.
INSP-Sprinkler Rough-in12/7/201612/8/201612/8/2016ACANC
DetailsTroy Cobbley
To be rescheduled for tomorrow morning per Jim and Perly
INSP-Sprinkler Rough-in12/6/201612/7/201612/7/2016ACANC
DetailsJim Page
Contact is Perly Daniels - RTC for Floors 1 thru 5 Phone #: ###-#### >> Inspection requested via web by Teri Cruickshank Inspection cancelled from web by: Teri Cruickshank