INSP-Final Inspection | 11/29/2016 | 11/29/2016 | 11/29/2016 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Final Inspection | 11/14/2016 | 11/16/2016 | 11/16/2016 | A | FAIL |
Troy Cobbley
|
|
|
Noted a painted head in the upstairs restroom of unit 9 and the two riser exceed 1 1/2" from the wall in the riser room.
|
INSP-Sprinkler Rough-in/Hydro | 11/1/2016 | 11/1/2016 | 11/1/2016 | P | PASS |
Troy Cobbley
|
|
|
Hydro test of the riser/header/FDC passed
|
INSP-Sprinkler Rough-in | 9/27/2016 | 9/27/2016 | 9/27/2016 | P | PASS |
Jim Page
|
|
|
Tenting inspection for overhead fire sprinkler piping complete, overhead fire sprinkler piping approved for cover.
|
INSP-Sprinkler Rough-in/Hydro | 9/23/2016 | 9/26/2016 | 9/26/2016 | P | FAIL |
Troy Cobbley
|
|
|
Riser manifold is still leaking
|
INSP-Sprinkler Rough-in | 9/1/2016 | 9/2/2016 | 9/2/2016 | A | FAIL |
Troy Cobbley
|
|
|
Tenting inspection failed due to missing insulation and insulation not attached. Robert Phone #: ###-####
|
INSP-Sprinkler Rough-in/Hydro | 9/1/2016 | 9/1/2016 | 9/1/2016 | P | PART |
Troy Cobbley
|
|
|
1st and 2nd floor hydro tests passed. The riser manifold hydro test failed due to a visable leak.
|
INSP-Sprinkler Rough-in | 8/24/2016 | 8/24/2016 | 8/24/2016 | P | PART |
Troy Cobbley
|
|
|
Rough-in passed except for one head that is missing in a second floor west end restroom. No tenting has been installed or inspected so no piping can be covered.
|