INSP-Final Inspection | 11/22/2016 | 11/23/2016 | 11/23/2016 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Final Inspection | 11/18/2016 | 11/22/2016 | 11/22/2016 | A | CANC |
Troy Cobbley
|
|
|
Joseph Danes is contact. He will be on site all day. Phone #: ###-#### Inspection requested via web by Connie Danes
|
INSP-Sprinkler Rough-in/Hydro | 11/17/2016 | 11/18/2016 | 11/18/2016 | A | PASS |
Troy Cobbley
|
|
|
Overhead hydro test passed
|
INSP-Sprinkler Rough-in/Hydro | 9/22/2016 | 9/23/2016 | 9/23/2016 | A | PASS |
Troy Cobbley
|
|
|
Rough-in passed. Tenting passed. Piping can be covered. As-builts to be provided
|
INSP-Sprinkler Rough-in | 9/16/2016 | 9/19/2016 | 9/19/2016 | P | CANC |
Troy Cobbley
|
|
|
Joseph Danes and I agreed to inspect this when the tenting has been installed.
|