INSP-Final Inspection | 2/28/2017 | 2/28/2017 | 2/28/2017 | P | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection passed/complete
|
INSP-Supply line flush | 2/8/2017 | 2/9/2017 | 2/9/2017 | P | DONE |
Jim Page
|
|
|
Underground main line flush complete
|
INSP-Sprinkler Rough-in | 10/20/2016 | 10/21/2016 | 10/21/2016 | A | PASS |
Jim Page
|
|
|
Rough to cover/tenting inspection complete for overhead fire sprinkler piping located in attic spaces on levels 2 and 3, overhead fire sprinkler for entire building approved for cover.
|
INSP-Sprinkler Rough-in | 10/19/2016 | 10/20/2016 | 10/20/2016 | A | FAIL |
Jim Page
|
|
|
Tenting inspection performed for overhead fire sprinkler piping located in attic spaces done, piping cannot be covered, numerous area's throughout level 3 has insulation going over the top of plumbing vent lines, pocket between sheetrock and piping will not be formed due to the spacing. Level 3 west apartments has miising insulation over the top of the piping in the living rooms, piping cannot be covered at this time.
|
INSP-Sprinkler Rough-in/Hydro | 10/13/2016 | 10/13/2016 | 10/13/2016 | P | PART |
Jim Page
|
|
|
Hydrostatic test complete for entire overhead fire sprinkler piping in building. Rough to cover inspection complete for overhead fire sprinkler piping. Level 1 overhead fire sprinkler piping approved for cover, level 2 overhead fire sprinkler piping located between levels approved for cover, overhead fire sprinkler piping located on level 2 that is in attic space cannot be covered until tenting inspection is performed. Level 3 overhead fire sprinkler piping cannot be covered until tenting inspection is complete. Will need to verify that an approved method has been accepted and installed to keep the pipe crossing the breezeway's from freezing, this will be verified at a later date.
|
INSP-Sprinkler Rough-in/Hydro | 9/19/2016 | 9/19/2016 | 9/19/2016 | P | CANC |
Jim Page
|
|
|
Inspection request was for another day, this inspection request cancelled per conversation with Jake, inspection request will be reschedule for when needed.
|
INSP-Sprinkler Rough-in/Hydro | 9/14/2016 | 9/15/2016 | 9/15/2016 | P | CANC |
Jim Page
|
|
|
Urgency for this inspection request is not required, inspection request can be reschedued, due to inspection load this inspection request will be rsescheduled per conversation with job foreman Jake.
|
INSP-Supply line flush | 7/20/2016 | 7/21/2016 | 7/21/2016 | A | PASS |
Jim Page
|
|
|
Inspection request was for underground hydrostatic test and underground rough to cover, not a flush. Underground hydrostatic test passed/complete, underground supply approved for cover, flush will be completed at a later date.
|
INSP-Supply line flush | 7/20/2016 | 7/21/2016 | 7/20/2016 | A | CANC |
Jim Page
|
|
|
Underground rough inspection. Phone #: ###-#### >> Inspection requested via web by Anthony Minichiello Inspection cancelled from web by: Anthony Minichiello
|