INSP-Final Inspection | 3/31/2017 | 4/3/2017 | 4/3/2017 | A | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection passed/complete
|
INSP-Final Inspection | 3/30/2017 | 3/31/2017 | 3/31/2017 | P | CANC |
Jim Page
|
|
|
Inspection request rescheduled for 8AM, 03APR2017
|
INSP-Supply line flush | 3/27/2017 | 3/28/2017 | 3/28/2017 | P | DONE |
Jim Page
|
|
|
Underground main line flush completed
|
INSP-Sprinkler Rough-in/Hydro | 3/17/2017 | 3/17/2017 | 3/17/2017 | P | PASS |
Jim Page
|
|
|
Underground hydro complete
|
INSP-Sprinkler Rough-in | 3/17/2017 | 3/17/2017 | 3/17/2017 | P | PASS |
Jim Page
|
|
|
Rough to cover inspection for underground supply complete, approved for cover.
|
INSP-Supply line flush | 3/17/2017 | 3/17/2017 | 3/17/2017 | P | CANC |
Jim Page
|
|
|
|
INSP-Supply line flush | 3/15/2017 | 3/16/2017 | 3/16/2017 | A | CANC |
Jim Page
|
|
|
Inspection request cancelled per conversation with point of contact Jake Phone #: ###-#### due to complications, request will be reschedule.
|
INSP-Sprinkler Rough-in/Hydro | 1/11/2017 | 1/12/2017 | 1/12/2017 | A | CANC |
Jim Page
|
|
|
Level 2 hydro completed on 11JAN2017
|
INSP-Sprinkler Rough-in/Hydro | 1/10/2017 | 1/11/2017 | 1/11/2017 | P | PASS |
Jim Page
|
|
|
Hydrostatic test complete for standpip. Hydrostatic test complete for overhead fire sprinkler piping on levels 1 and 2.
|
INSP-Sprinkler Rough-in/Hydro | 12/30/2016 | 1/4/2017 | 1/4/2017 | P | PART |
Jim Page
|
|
|
Rough to cover ispection for overhead fire sprinkler piping on levels 1 and 2 complete, approved for cover, hydrostatic test will be completed at a later date.
|
INSP-Sprinkler Rough-in | 1/3/2017 | 1/3/2017 | 1/3/2017 | P | PASS |
Jim Page
|
|
|
Tenting inspection for level 3 fire sprinkler piping in attic spaces complete, approved for cover.
|
INSP-Sprinkler Rough-in/Hydro | 12/29/2016 | 12/30/2016 | 12/30/2016 | P | CANC |
Jim Page
|
|
|
Hydrostatic test cancelled by point of contact due to weather conditions.
|
INSP-Sprinkler Rough-in/Hydro | 12/22/2016 | 12/23/2016 | 12/23/2016 | P | CANC |
Jim Page
|
|
|
Inspection request cancelled per conversation with Anthony due to weahter conditions, inspection request will be rescheduled.
|
INSP-Sprinkler Rough-in/Hydro | 12/21/2016 | 12/22/2016 | 12/22/2016 | P | CANC |
Jim Page
|
|
|
First and second floors, and standpipes. Call Anthony when heading out, thanks! Phone #: ###-#### >> Inspection requested via web by Anthony Minichiello Inspection cancelled from web by: Anthony Minichiello
|
INSP-Sprinkler Rough-in/Hydro | 12/20/2016 | 12/20/2016 | 12/20/2016 | P | PART |
Jim Page
|
|
|
Rough to cover inspection for overhead fire sprinkler piping complete for levels 3 and 4, all overhead fire sprinkler piping on level 4 approved for cover, will need to verify heat for breezeway crossings at a later date, overhead fire sprinkler piping located between floor levels on level 3 approved for cover, tenting was not installed over piping in attic space on level 3 so piping located in attic space on level 3 cannot be covered until tenting is installed and inspected. Hydrostatic test for overhead fire sprinkler piping on levels 3 and 4 passed/complete.
|
INSP-Sprinkler Rough-in/Hydro | 12/16/2016 | 12/19/2016 | 12/19/2016 | A | CANC |
Jim Page
|
|
|
Tenting is not completely installed over the top of overhead fire sprinkler piping. Piping cannot be covered until tenting is complete, inspection request cancelled per conversation with contractor.
|