INSP-Final Inspection | 6/1/2017 | 6/2/2017 | 6/2/2017 | P | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection passed/complete
|
INSP-Supply line flush | 5/4/2017 | 5/5/2017 | 5/5/2017 | A | DONE |
Jim Page
|
|
|
Underground main line flush complete
|
INSP-Sprinkler Rough-in/Hydro | 4/10/2017 | 4/10/2017 | 4/10/2017 | P | PASS |
Jim Page
|
|
|
First floor hydrostatic test complete
|
INSP-Sprinkler Rough-in/Hydro | 3/27/2017 | 3/28/2017 | 3/28/2017 | P | CANC |
Jim Page
|
|
|
First Floor Hydro cancelled due to test pump issues, hydro will be rescheduled
|
INSP-Sprinkler Rough-in | 3/24/2017 | 3/24/2017 | 3/24/2017 | P | PASS |
Jim Page
|
|
|
Rough to cover inspection for overhead fire sprinkler piping/tenting complete, approved for cover.
|
INSP-Sprinkler Rough-in/Hydro | 3/21/2017 | 3/22/2017 | 3/22/2017 | P | PART |
Jim Page
|
|
|
Hydrostatic test for overhead fire sprinkler piping complete for levels 2, 3 and 4, level one did not pass hydrostatic test, visible leak on the overhead fire sprinkler piping as well as pressure loss at gauge. Rough to cover inspection complete for levels 1 and 2, levels 1 and 2 approved for cover. Rough in inspection complete for levels 3 and 4, partial cover allowed on level 3, fire sprinkler piping located in attic space cannot be covered until tenting inspection is complete, overhead fire sprinkler piping in attic space cannot be covered until tenting inspection is complete.
|
INSP-Sprinkler Rough-in/Hydro | 3/20/2017 | 3/21/2017 | 3/21/2017 | P | CANC |
Scott Arellano
|
|
|
Call Jake when heading out, thanks! Phone #: ###-#### >> Inspection requested via web by Anthony Minichiello Inspection cancelled from web by: Anthony Minichiello
|
INSP-Supply line flush | 3/7/2017 | 3/8/2017 | 3/8/2017 | P | PART |
Jim Page
|
|
|
Inspection request is for underground rough/hydro, not supply line flush. Underground rough to cover inspection complete, underground hydro complete.
|
INSP-Sprinkler Rough-in/Hydro | 2/28/2017 | 2/28/2017 | 2/28/2017 | P | PART |
Jim Page
|
|
|
Rough to cover inspection complete for overhead fire sprinkler piping, room 102 on level 1 cannt be covered, FDC piping needs hanges installed before cover is allowed. Level 2 approved for cover, partial cover allowed for level 3, piping in attic spaces on level 3 and 4 cannot be covered until tenting is installed, inspected and passed.
|
INSP-Sprinkler Rough-in/Hydro | 2/9/2017 | 2/9/2017 | 2/9/2017 | P | PASS |
Jim Page
|
|
|
Rough in/hydro for standpipe complete
|
INSP-Sprinkler Rough-in/Hydro | 2/8/2017 | 2/8/2017 | 2/8/2017 | P | CANC |
Jim Page
|
|
|
Standpipe rough/hydro inspection cancelled per conversation with point of contact, Jake Phone #: ###-####, inspection request will be scheduled for a later date.
|
INSP-Sprinkler Rough-in/Hydro | 1/26/2017 | 1/27/2017 | 1/27/2017 | A | CANC |
Jim Page
|
|
|
Standpipe rough/air test for hydro. Call Jake when heading out, thanks! Phone #: ###-#### >> Inspection requested via web by Anthony Minichiello Inspection cancelled from web by: Anthony Minichiello
|