Permit Information
Permit NumberFIR16-00524
StatusFinaled
Name SHILO AUTOMATIC SPRINKLER CO
Site Address 850 W FRONT ST
Project NameElevated Concourse Boise Centr
Customer Number 
ePlanReviewYes
Description
[Boise Centre Walkway] - Quick Permit
Cut, cap and re-rout an existing fire sprinkler line and demo remain fire sprinkler components to facilitate the demo of existing overhead structure.

[BLD15-04468] - Fire sprinkler systems used for high-rise and for occupancy. To expand a portion of the existing Boise Centre Convention building by constructing a 2nd story to create a vertical circulation route to a new elevated pedestrian walkway and enclosed elevated concourse that will connect the Boise Centre Convention building to the City Center Plaza building (3,603 square feet total). The floor of the new elevated circulation route will be located about 24 feet above grade, at the perimeter of The Grove. The concourse will be part of the Century Link Arena building. A terrace will also be constructed at the Boise Centre Convention building adjacent to The Grove. Work is to include an elevator, an escalator, two egress stairways, exterior walls, interior doors, and finishes. Structural work includes micro piles, helical piers, concrete footings, concrete foundations, steel columns, steel beams, a moment frame, a horizontal truss, steel pan deck and concrete floors, masonry walls, etc. Special Inspection is required for fabricators, steel, welding, concrete, masonry, soils, cast-in-place deep foundations (micro piles), helical piers, epoxy anchors, other post installed concrete anchors, seismic resistance, bolting, and spray-applied fire resistant materials. Post tensioned concrete slabs are required to be scanned to locate rebar, including tendons, before any holes are drilled. No rebar, including tendons, are allowed to be cut. Structural observations by the Structural Engineer of Record will be provided as noted on the drawings. The stairway design is a deferred submittal item. Property easements are required to allow construction within CCDC property. The work is required to comply with the approved drawings, with the plan review report, with the structural design, with the approved code alternates, and with all applicable codes and ordinances. The fire sprinkler system is required to comply with NFPA 13 and the fire alarm system is required to comply with NFPA 72 as regulated by the Fire Department. Separate fire sprinkler permits and fire alarm permits shall be obtained prior to beginning any modification or installation work on such systems. **CJW**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection6/28/20176/29/20176/29/2017PPASS
DetailsJim Page
Final fire sprinkler inspection passed/complete