INSP-Final Inspection | 12/8/2016 | 12/9/2016 | 12/9/2016 | A | PASS |
Jim Page
|
|
|
Short wall mount PIV in place, operation verified. Final inspectio for fire sprinklers passed/complete.
|
INSP-Final Inspection | 12/7/2016 | 12/8/2016 | 12/8/2016 | A | CANC |
Troy Cobbley
|
|
|
Cancel per Colton Phone #: ###-####
|
INSP-Final Inspection | 11/30/2016 | 12/1/2016 | 12/1/2016 | A | CANC |
Troy Cobbley
|
|
|
Coltan Phone #: ###-####
|
INSP-Final Inspection | 11/30/2016 | 11/30/2016 | 11/30/2016 | P | PART |
Troy Cobbley
|
|
|
A temporary for the fire sprinkler permit is ok until the new, shorter, wall PIV has been installed and tested. Supposed arrival date for the new PIV is 12-7-16
|
INSP-Sprinkler Rough-in/Hydro | 11/30/2016 | 11/30/2016 | 11/30/2016 | P | PASS |
Troy Cobbley
|
|
|
Overhead hydro test passed. Rough-in for the two new pendants passed. Piping can be covered.
|
INSP-Final Inspection | 11/28/2016 | 11/29/2016 | 11/29/2016 | P | CANC |
Troy Cobbley
|
|
|
Robert Phone #: ###-####
|
INSP-Sprinkler Rough-in | 11/28/2016 | 11/29/2016 | 11/29/2016 | A | FAIL |
Troy Cobbley
|
|
|
Two pendants need to be added in the Bakery Area. Fire dept needs to approve the location/blockage of the FDC.
|
INSP-Sprinkler Rough-in/Hydro | 11/28/2016 | 11/29/2016 | 11/29/2016 | A | FAIL |
Troy Cobbley
|
|
|
Can not due hydro because of the two heads that need to be added in the Bakery Area.
|
INSP-Sprinkler Rough-in/Hydro | 11/22/2016 | 11/22/2016 | 11/22/2016 | P | FAIL |
Troy Cobbley
|
|
|
Could not perform the hydro test due to pendant heads needing to be located in ceiling. Much of the ceiling needs to be removed because no cover inspection has been performed.
|
INSP-Sprinkler Rough-in | 10/17/2016 | 10/17/2016 | 10/17/2016 | P | PART |
Troy Cobbley
|
|
|
See the city aproved plans for piping above hardlids that is marked "ok" for cover.
|
INSP-Conference | 10/5/2016 | 10/5/2016 | 10/5/2016 | P | DONE |
Troy Cobbley
|
|
|
Rick Phone #: ###-#### wanted to know if I would be ok with the fire dept connection being mounted at 42". I stated that was ok.
|
INSP-Supply line flush | 10/3/2016 | 10/3/2016 | 10/3/2016 | P | PASS |
Troy Cobbley
|
|
|
The underground supply line hydro test passed.
|
INSP-Supply line flush | 9/30/2016 | 9/30/2016 | 9/30/2016 | P | PASS |
Troy Cobbley
|
|
|
Underground flush passed.
|
INSP-Sprinkler Rough-in | 8/30/2016 | 8/30/2016 | 8/31/2016 | P | PASS |
Troy Cobbley
|
|
|
Remaining underground supply piping is ok to cover
|
INSP-Sprinkler Rough-in | 8/19/2016 | 8/19/2016 | 8/19/2016 | P | DONE |
Katie Marron
|
|
|
UDG cover from riser stub up to 5ft from bldg slab ok to cover.
|