Permit Information
Permit NumberFIR16-00540
StatusFinaled
Name SHILO AUTOMATIC SPRINKLER CO
Site Address 8401 W FRANKLIN RD
Project NamePanera Bread #1887
Customer Number 
ePlanReviewYes
Description
[Panera Bread Cafe #1887]
The fire sprinkler scope of work consists of new 6” x 231’ C-900 underground piping with necessary fittings and thrust blocks. A 4” riser with backflow preventer to 4” mains and 1 ½” center fed branch lines. The system is protected per NFPA 13 for OH 2 with above and below protection.

[BLD16-01452] - Permit to construct a 5,100 SF bakery/cafe with a drive-thru along Franklin Road and associated site work. Reduced interior lighting power is the additional efficiency package. Scope of work to include demolition of existing building, foundation, exterior walls, roof structure, interior finish, exterior canopies/awnings, plumbing, mechanical and electrical work as shown on approved drawings. This building is fully Fire Sprinklered with an approved Fire Alarm system. Any alterations or modifications to the buildings Fire Sprinkler or Fire Alarm system WILL REQUIRE A SEPARATE PERMIT and shall be installed per NFPA 13 & NFPA 72 as regulated by the Boise Fire Department. **ajs**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection12/8/201612/9/201612/9/2016APASS
DetailsJim Page
Short wall mount PIV in place, operation verified. Final inspectio for fire sprinklers passed/complete.
INSP-Final Inspection12/7/201612/8/201612/8/2016ACANC
DetailsTroy Cobbley
Cancel per Colton Phone #: ###-####
INSP-Final Inspection11/30/201612/1/201612/1/2016ACANC
DetailsTroy Cobbley
Coltan Phone #: ###-####
INSP-Final Inspection11/30/201611/30/201611/30/2016PPART
DetailsTroy Cobbley
A temporary for the fire sprinkler permit is ok until the new, shorter, wall PIV has been installed and tested. Supposed arrival date for the new PIV is 12-7-16
INSP-Sprinkler Rough-in/Hydro11/30/201611/30/201611/30/2016PPASS
DetailsTroy Cobbley
Overhead hydro test passed. Rough-in for the two new pendants passed. Piping can be covered.
INSP-Final Inspection11/28/201611/29/201611/29/2016PCANC
DetailsTroy Cobbley
Robert Phone #: ###-####
INSP-Sprinkler Rough-in11/28/201611/29/201611/29/2016AFAIL
DetailsTroy Cobbley
Two pendants need to be added in the Bakery Area. Fire dept needs to approve the location/blockage of the FDC.
INSP-Sprinkler Rough-in/Hydro11/28/201611/29/201611/29/2016AFAIL
DetailsTroy Cobbley
Can not due hydro because of the two heads that need to be added in the Bakery Area.
INSP-Sprinkler Rough-in/Hydro11/22/201611/22/201611/22/2016PFAIL
DetailsTroy Cobbley
Could not perform the hydro test due to pendant heads needing to be located in ceiling. Much of the ceiling needs to be removed because no cover inspection has been performed.
INSP-Sprinkler Rough-in10/17/201610/17/201610/17/2016PPART
DetailsTroy Cobbley
See the city aproved plans for piping above hardlids that is marked "ok" for cover.
INSP-Conference10/5/201610/5/201610/5/2016PDONE
DetailsTroy Cobbley
Rick Phone #: ###-#### wanted to know if I would be ok with the fire dept connection being mounted at 42". I stated that was ok.
INSP-Supply line flush10/3/201610/3/201610/3/2016PPASS
DetailsTroy Cobbley
The underground supply line hydro test passed.
INSP-Supply line flush9/30/20169/30/20169/30/2016PPASS
DetailsTroy Cobbley
Underground flush passed.
INSP-Sprinkler Rough-in8/30/20168/30/20168/31/2016PPASS
DetailsTroy Cobbley
Remaining underground supply piping is ok to cover
INSP-Sprinkler Rough-in8/19/20168/19/20168/19/2016PDONE
DetailsKatie Marron
UDG cover from riser stub up to 5ft from bldg slab ok to cover.