INSP-Final Inspection | 7/12/2017 | 7/13/2017 | 7/13/2017 | A | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection passed/complete
|
INSP-Sprinkler Rough-in | 5/30/2017 | 5/31/2017 | 5/31/2017 | A | PASS |
Scott Arellano
|
|
|
Fire sprinkler main heat traced and will be insulated at east side unheated area, access hatch provided, monitoring module installed. Testing of module will take place at fire alarm inspection. Ok to cover.
|
INSP-Sprinkler Rough-in | 5/24/2017 | 5/25/2017 | 5/25/2017 | A | PART |
Jim Page
|
|
|
Rough to cover inspection for tenting on pod 3 complete, approved for cover.
|
INSP-Sprinkler Rough-in | 5/8/2017 | 5/9/2017 | 5/9/2017 | A | PART |
Jim Page
|
|
|
Rough to cover inspection for tenting on pod 4 complete, approved for cover.
|
INSP-Sprinkler Rough-in/Hydro | 4/26/2017 | 4/27/2017 | 4/27/2017 | A | PART |
Jim Page
|
|
|
Hydrostatic complete for overhead fire sprinkler piping. Rough to cover inspection complete for levels 1 and 2 of pod 4, rough in inspection complete for level 3, tenting to be installed at a later date.
|
INSP-Sprinkler Rough-in/Hydro | 4/26/2017 | 4/26/2017 | 4/26/2017 | P | CANC |
Jim Page
|
|
|
Inspection request rescheduled per conversation with Mike Phone #: ###-####
|
INSP-Sprinkler Rough-in | 4/11/2017 | 4/11/2017 | 4/11/2017 | P | PART |
Jim Page
|
|
|
Rough to cover inspection for levels 1 and 2 of pod 3 complete, approved for cover. Rough in inspection complete for level 3, tenting needs to be installed/inspected and passed before cover can be approved.
|
INSP-Sprinkler Rough-in/Hydro | 4/3/2017 | 4/4/2017 | 4/4/2017 | A | PART |
Jim Page
|
|
|
Tenting inspection for south east apartment unit of pod 2, level 3 complete, approved for cover.
|
INSP-Sprinkler Rough-in | 3/31/2017 | 4/3/2017 | 4/3/2017 | A | PART |
Jim Page
|
|
|
Rough to cover inspection for overhead fire sprinkler pipe tenting partially complete, approved for cover except the south east apartment unit of pod 2, level 3, no insualtion installed
|
INSP-Conference | 3/7/2017 | 3/7/2017 | 3/7/2017 | A | DONE |
Jim Page
|
|
|
Fire conference complete for soffit addition in residant rooms for fresh air vent, heads will spray under soffit with adjusted spacing of room heads.
|
INSP-Sprinkler Rough-in/Hydro | 2/27/2017 | 2/28/2017 | 2/28/2017 | A | PART |
Jim Page
|
|
|
Tenting inspection for pod 1, level 3 complete, approved for cover.
|
INSP-Sprinkler Rough-in | 2/24/2017 | 2/27/2017 | 2/27/2017 | A | CANC |
Jim Page
|
|
|
3RD FLOOR tenting inspection request is rescheduled for 28FEB2017 per conversation with general contractor.
|
INSP-Sprinkler Rough-in | 2/23/2017 | 2/24/2017 | 2/24/2017 | A | PART |
Jim Page
|
|
|
Rough to cover inspection for Pod 2 complete, levels 1 and 2 approved for cover, level 3 cannot be completed until tenting inspection is complete.
|
INSP-Supply line flush | 2/14/2017 | 2/16/2017 | 2/16/2017 | A | DONE |
Jim Page
|
|
|
Underground main line flush complete
|
INSP-Sprinkler Rough-in/Hydro | 2/13/2017 | 2/14/2017 | 2/14/2017 | A | PASS |
Jim Page
|
|
|
Underground hydrostatic test complete
|
INSP-Sprinkler Rough-in/Hydro | 2/10/2017 | 2/10/2017 | 2/10/2017 | P | PART |
Jim Page
|
|
|
Partial rough to cover inspection complete for levels 1, mezzanine, and level 2, notated the city approved drawings with yellow highlighter red ink area's approved for cover. Rough in inspection is complete for level 3 in highlighted area on city approved drawings. Level 3 piping cannot be covered until tenting inspection is complete and passed.
|