INSP-Final Inspection | 3/1/2018 | 3/5/2018 | 3/5/2018 | P | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection complete.
|
INSP-Sprinkler Rough-in | 8/29/2017 | 8/29/2017 | 8/29/2017 | P | PASS |
Jim Page
|
|
|
Rough to cover inspection for overhead fire sprinkler piping/tenting complete, approved for cover.
|
INSP-Sprinkler Rough-in/Hydro | 8/15/2017 | 8/15/2017 | 8/15/2017 | P | PASS |
Troy Cobbley
|
|
|
Above ground hydro test for both systems passed
|
INSP-Supply line flush | 8/2/2017 | 8/3/2017 | 8/3/2017 | A | DONE |
Jim Page
|
|
|
Underground main line flush complete
|
INSP-Sprinkler Rough-in | 5/16/2017 | 5/17/2017 | 5/17/2017 | A | PASS |
Troy Cobbley
|
|
|
The underground supply piping is ok to cover
|