Permit Information
Permit NumberFIR16-00707
StatusFinaled
Name SHILO AUTOMATIC SPRINKLER CO
Site Address 850 W FRONT ST
Project NameElevated Concourse Boise Centr
Customer Number 
ePlanReviewYes
Description
[City Center Plaza - Elevated Concourse]
The fire sprinkler scope of work consists of protecting the elevated concourse and associated areas per an alternate agreement. (See Addendum) Only a few small areas on the grade level have protection at the property lines. See addendum for complete clarification.

[BLD15-04468] - (BOISE CENTRE LOBBY EXPANSION, TERRACE, PEDESTRIAN WALKWAY, AND CONCOURSE) (DRH15-00462) Fire sprinkler systems used for high-rise and for occupancy. To expand a portion of the existing Boise Centre Convention building by constructing a 2nd story to create a vertical circulation route to a new elevated pedestrian walkway and enclosed elevated concourse that will connect the Boise Centre Convention building to the City Center Plaza building (3,603 square feet total). The floor of the new elevated circulation route will be located about 24 feet above grade, at the perimeter of The Grove. The concourse will be part of the Century Link Arena building. A terrace will also be constructed at the Boise Centre Convention building adjacent to The Grove. Work is to include an elevator, an escalator, two egress stairways, exterior walls, interior doors, and finishes. Structural work includes micro piles, helical piers, concrete footings, concrete foundations, steel columns, steel beams, a moment frame, a horizontal truss, steel pan deck and concrete floors, masonry walls, etc. Special Inspection is required for fabricators, steel, welding, concrete, masonry, soils, cast-in-place deep foundations (micro piles), helical piers, epoxy anchors, other post installed concrete anchors, seismic resistance, bolting, and spray-applied fire resistant materials. Post tensioned concrete slabs are required to be scanned to locate rebar, including tendons, before any holes are drilled. No rebar, including tendons, are allowed to be cut. Structural observations by the Structural Engineer of Record will be provided as noted on the drawings. The stairway design is a deferred submittal item. Property easements are required to allow construction within CCDC property. The work is required to comply with the approved drawings, with the plan review report, with the structural design, with the approved code alternates, and with all applicable codes and ordinances. The fire sprinkler system is required to comply with NFPA 13 and the fire alarm system is required to comply with NFPA 72 as regulated by the Fire Department. Separate fire sprinkler permits and fire alarm permits shall be obtained prior to beginning any modification or installation work on such systems. **CJW**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection6/28/20176/29/20176/29/2017PPASS
DetailsJim Page
Final fire sprinkler inspection passed/complete
INSP-Sprinkler Rough-in/Hydro3/28/20173/29/20173/29/2017APART
DetailsJim Page
Fire sprinkler work for requested TCO area's complete (Link between GBAD, Century Link Arena, Boise Center on the Grove as well as escalators from link and lobby are for escalator discharge)
INSP-Final Inspection3/27/20173/28/20173/28/2017PCANC
DetailsJim Page
Inspection rescheduled to coincide with life fire safety inspection
INSP-Sprinkler Rough-in/Hydro3/23/20173/23/20173/23/2017APASS
DetailsTim Frost
Passed 24 hour air test on dry system
INSP-Sprinkler Rough-in/Hydro3/21/20173/21/20173/21/2017PPASS
DetailsTim Frost
Hydro passed on elevated concourse phase 2
INSP-Sprinkler Rough-in/Hydro3/17/20173/20/20173/20/2017PCANC
DetailsTroy Cobbley
Cancel per Scott
INSP-Sprinkler Rough-in/Hydro3/8/20173/9/20173/9/2017PPART
DetailsJim Page
Rough to cover inspection compete for overhead fire sprinkler piping on level 2 and level 1 entry by escalators, approved for cover. Hydro will be completed at a later date.
INSP-Sprinkler Rough-in2/13/20172/14/20172/14/2017APART
DetailsJim Page
Partial rough to cover inspection complete for fire sprinkler piping located above hardlids, northside wet and dry systems on level 2, notated city approved drawings with pink highlighter area's approved for cover.