INSP-Final Inspection | 8/1/2017 | 8/2/2017 | 8/2/2017 | A | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection passed/complete
|
INSP-Supply line flush | 6/14/2017 | 6/15/2017 | 6/15/2017 | A | PASS |
Troy Cobbley
|
|
|
underground flush passed
|
INSP-Sprinkler Rough-in/Hydro | 5/2/2017 | 5/3/2017 | 5/3/2017 | A | PASS |
Jim Page
|
|
|
Hydrostatic test for overhead fire sprinkler piping located on level 4 complete, rough to cover inspection for overhead fire sprinkler piping/tenting on fre fire sprinkler piping located in attic spaces compete, approved for cover.
|
INSP-Sprinkler Rough-in/Hydro | 5/2/2017 | 5/2/2017 | 5/2/2017 | P | CANC |
Jim Page
|
|
|
Inspection request rescheduled for 3MAY2017
|
INSP-Sprinkler Rough-in/Hydro | 4/24/2017 | 4/25/2017 | 4/25/2017 | A | PART |
Jim Page
|
|
|
Hydrostatic test complete for levels 2 and 3, rough to cover inspection complete for level 2, level 2 approved for cover, partial cover approved for level 3, overhead fire sprinkler piping in attic space cannot be covered until tenting is installed and passed inspection.
|
INSP-Sprinkler Rough-in/Hydro | 4/24/2017 | 4/24/2017 | 4/24/2017 | P | CANC |
Jim Page
|
|
|
Inspection request cancelled per conversation with Jake ###-#### Inspection requested will be rescheduled by contractor.
|
INSP-Sprinkler Rough-in/Hydro | 4/19/2017 | 4/21/2017 | 4/21/2017 | P | PART |
Jim Page
|
|
|
Rough to cover inspection for overhead fire sprinkler piping on level 1 complete, approved for cover on level 1 only. Hydrostatic test complete for overhead fire sprinkler piping on level 1, levels 2, 3 and 4 to have hydrostatic test completed at a later date.
|
INSP-Sprinkler Rough-in/Hydro | 3/22/2017 | 3/22/2017 | 3/22/2017 | P | PASS |
Jim Page
|
|
|
Underground hydrostatic test complete
|
INSP-Supply line flush | 3/21/2017 | 3/22/2017 | 3/22/2017 | P | CANC |
Jim Page
|
|
|
Incorrect inspection request, request is for an underground hydro, this request cancelled and the correct request generated.
|
INSP-Sprinkler Rough-in/Hydro | 3/20/2017 | 3/23/2017 | 3/21/2017 | P | CANC |
Jim Page
|
|
|
Underground rough/hydro - call Jake when heading out, thanks! Phone #: ###-#### >> Inspection requested via web by Anthony Minichiello Inspection cancelled from web by: Anthony Minichiello
|
INSP-Supply line flush | 3/20/2017 | 3/21/2017 | 3/20/2017 | P | CANC |
Jim Page
|
|
|
Underground rough/hydro - call Jake when heading out. Phone #: ###-#### >> Inspection requested via web by Anthony Minichiello Inspection cancelled from web by: Anthony Minichiello
|
INSP-Sprinkler Rough-in | 3/17/2017 | 3/17/2017 | 3/17/2017 | P | PASS |
Jim Page
|
|
|
Rough to cover inspection for underground supply complete, approved for cover.
|
INSP-Supply line flush | 3/17/2017 | 3/17/2017 | 3/17/2017 | P | CANC |
Jim Page
|
|
|
|
INSP-Supply line flush | 3/15/2017 | 3/16/2017 | 3/16/2017 | A | CANC |
Jim Page
|
|
|
Inspection request cancelled per conversation with point of contact Jake Phone #: ###-#### due to complications, request will be reschedule.
|
INSP-Sprinkler Rough-in/Hydro | 2/9/2017 | 2/9/2017 | 2/9/2017 | P | PASS |
Jim Page
|
|
|
Rough in/hydro for standpipe complete
|
INSP-Sprinkler Rough-in/Hydro | 2/8/2017 | 2/8/2017 | 2/8/2017 | P | CANC |
Jim Page
|
|
|
Standpipe rough/hydro inspection cancelled per conversation with point of contact, Jake Phone #: ###-####, inspection request will be scheduled for a later date.
|