INSP-Final Inspection | 3/20/2017 | 3/21/2017 | 3/21/2017 | A | PASS |
Troy Cobbley
|
|
|
permit finaled
|
INSP-Final Inspection | 3/8/2017 | 3/9/2017 | 3/9/2017 | A | FAIL |
Troy Cobbley
|
|
|
Permit can be finaled when the as-builts are approved.
|
INSP-Final Inspection | 2/20/2017 | 2/21/2017 | 2/21/2017 | A | FAIL |
Troy Cobbley
|
|
|
New panel tested ok and signals have been verified. Problem is the visual notificaion devices are not sync'd. Provide sync of visual and as-builts showing sync module/changes.
|
INSP-Final Inspection | 2/16/2017 | 2/17/2017 | 2/17/2017 | A | FAIL |
Troy Cobbley
|
|
|
Phone lines had not been programed to call out so testing on my part was stopped that that the contractor could perform their required testing. Scott stated that the existing manual pull stations and notification devices that do not meet code heigth requirements can remain due to this specific scope of work. Also Tony is doing a great job of cleaning up the wiring in the panel.
|