INSP-Final Inspection | 9/10/2017 | 9/11/2017 | 9/11/2017 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Final Inspection | 9/6/2017 | 9/7/2017 | 9/7/2017 | A | PART |
Troy Cobbley
|
|
|
A temporary for the fire alarm permit is being given with Scotts approval until the as-builts and record of completion has been provided.
|
INSP-Final Inspection | 9/5/2017 | 9/6/2017 | 9/6/2017 | A | FAIL |
Troy Cobbley
|
|
|
Need the correct as-builts, map at the facp, test security doors interface, and record of completion.
|
INSP-Final Inspection | 9/4/2017 | 9/5/2017 | 9/5/2017 | A | FAIL |
Troy Cobbley
|
|
|
Arrived first thing in the morning to begin testing and found that the central station had not made the required changes to the device descriptions. I went back in the afternoon and was able to verify that the sprinkler system interconnections now are correct.
|
INSP-Final Inspection | 8/31/2017 | 9/1/2017 | 9/1/2017 | A | FAIL |
Troy Cobbley
|
|
|
Todays inspection was just a partial. Installed head end equipment tested ok, manual pull statons tested ok, hood suppression system tested ok. The sprinkler system interconnections have problems as the tamper switches and pressure switches report as a/c power loss. All notification devices tested ok and are sync'd. Need to re-verify the fire sprinkler interconnects, duct detectors, fire door release, security door release, smoke detectors and heat detectors. I verified off site monitoring for the devices tested. Address was ok. Will need as-builts showing the minimal changes.
|