INSP-Final Inspection | 8/7/2019 | 8/7/2019 | 8/7/2019 | P | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection for area of work complete.
Phone #: ###-#### Inspection requested via web by Jessia Maxwell
|
INSP-Final Inspection | 7/31/2019 | 8/1/2019 | 8/1/2019 | A | CANC |
Troy Cobbley
|
|
|
Canceling due to manpower shortage and time constraints. Please call Clarence Phone #: ###-#### Inspection requested via web by Jessia Maxwell
|
INSP-Final Inspection | 7/31/2019 | 7/31/2019 | 7/31/2019 | P | CANC |
Jim Page
|
|
|
Rescheduled for 01AUG2019 per conversation with point of contact, this request is cancelled.
Please call Clarence Phone #: ###-#### Inspection requested via web by Jessia Maxwell
|
INSP-Sprinkler Rough-in | 8/23/2017 | 8/24/2017 | 8/24/2017 | A | PART |
Jim Page
|
|
|
Rough to cover inspection for overhead fire sprinkler piping on systems 10-3, 20-7 and 20-11 complete, approved for cover. Notated the city approved drawings with green highlighter/red ink systems that were inspected.
|
INSP-Sprinkler Rough-in/Hydro | 8/23/2017 | 8/23/2017 | 8/23/2017 | P | PASS |
Jim Page
|
|
|
Hydrostatic test for systems 10-3, 20-7 and 20-11 complete.
|