Permit Information
Permit NumberFIR17-00090
StatusFinaled
Name TREASURE VALLEY FIRE PROTECTION
Site Address 8854 W EMERALD ST Unit: 200
Project NameKENDALL AUTO GROUP NAFCO TI
Customer Number 
ePlanReviewYes
Description
[Kendall Auto Group NAFCO] - Quick Permit
INSTALL NEW PENDENT HEADS TO THE NEW WALL AND CEILING LAYOUT.

[BLD16-04597] - Permit is to remodel existing 2,243 sq. ft. office space on the second floor. This permit is approved contingent upon adhering to the approved plans on file. Work to include: @ suite #200 removal of select interior nonbearing walls, removal of select door/door frames, removal of select ceiling, removal of select soffit, construction of select interior non-bearing walls to create a flex/break room area , open office area, (1) lactation room and men’s and women’s restrooms that are accessible to the disabled, new millwork, select new door/door frames, select new gypsum and suspended acoustic ceiling, new light fixtures, electrical work, mechanical work, plumbing work and interior finishes in compliance with chapter 8 of the 2012 IBC. @ suite #260 removal of select interior nonbearing walls, removal of select door/door frames and relocate, removal of select ceiling, removal of select millwork, construction of select interior non-bearing walls to create a conference room and a break room, new millwork, select new suspended acoustic ceiling, new light fixtures, electrical work, mechanical work, plumbing work and interior finishes in compliance with chapter 8 of the 2012 IBC. This building is fully fire sprinklered any alterations or modifications to the buildings Fire Sprinkler or Fire Alarm system WILL REQUIRE A SEPARATE PERMIT and shall be installed per NFPA 13 & NFPA 72 as regulated by the Boise Fire Department. **JG**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection4/28/20175/1/20175/1/2017APASS
DetailsTroy Cobbley
Permit finaled
INSP-Sprinkler Rough-in4/26/20174/26/20174/26/2017PPASS
DetailsJim Page
Rough to cover inspection for overhead fire sprinkler piping/pendant heads complete for breakroom and conference room, breakroom and conference room approved for cover.
INSP-Final Inspection3/29/20173/30/20173/30/2017APART
DetailsTroy Cobbley
Sprinkler work is complete in the second floor south east corner office remodel. Waiting for the conference room/office area to be completed before a final is given.
INSP-Final Inspection3/21/20173/21/20173/21/2017PFAIL
DetailsTroy Cobbley
Project is not ready for final due to missing ceilings.

Adam Phone #: ###-####
INSP-Sprinkler Rough-in3/16/20173/16/20173/16/2017PPASS
DetailsTroy Cobbley
Rough-in passed. Remaining piping can be covered.
INSP-Sprinkler Rough-in3/2/20173/3/20173/3/2017APASS
DetailsTroy Cobbley
The piping above both new restrooms and the entry is ok for cover and is marked on the plans