INSP-Final Inspection | 7/28/2017 | 7/28/2017 | 7/28/2017 | P | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection passed/complete
|
INSP-Final Inspection | 6/22/2017 | 6/23/2017 | 6/23/2017 | P | PART |
Jim Page
|
|
|
Final inspection complete for overhead fire sprinkler system. Items to be addressed before final life fire safety inspection: Upright head that is located to far down from the ceiling in wash room needs to be removed, head in cooler area next to the bar has overspray paint on the glass bulb (sprinkler head cannot be cleaned, sprinkler head must be replaced), wires hanging/attached to main and branch lines in south corridor cannot be attached to sprinkler piping and need to be supported on thier own hangers.
|
INSP-Sprinkler Rough-in | 4/3/2017 | 4/4/2017 | 4/4/2017 | P | PASS |
Jim Page
|
|
|
Rough to cover inspection for overhead fire sprinkler piping/pendant heads in area of work complete, area of work approved for cover.
|