INSP-Final Inspection | 12/8/2017 | 12/11/2017 | 12/11/2017 | A | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection complete.
|
INSP-Sprinkler Rough-in/Hydro | 12/8/2017 | 12/8/2017 | 12/8/2017 | P | DONE |
Troy Cobbley
|
|
|
Overhead hydro test complete
|
INSP-Supply line flush | 12/1/2017 | 12/5/2017 | 12/5/2017 | A | PASS |
Troy Cobbley
|
|
|
Underground flush passed
Phone #: ###-#### Inspection requested via web by Sam Ball
|
INSP-Sprinkler Rough-in | 10/3/2017 | 10/4/2017 | 10/4/2017 | P | PASS |
Troy Cobbley
|
|
|
Rough-in passed piping can be covered. Tenting passed
|
INSP-Sprinkler Rough-in | 9/20/2017 | 9/21/2017 | 9/21/2017 | P | PASS |
Troy Cobbley
|
|
|
Underground supply piping can be buried.
|
INSP-Sprinkler Rough-in | 9/20/2017 | 9/20/2017 | 9/20/2017 | P | FAIL |
Troy Cobbley
|
|
|
Underground supply piping does not meet the min. 4'6" bury depth.
|