Information based on query as of Friday, June 28, 2024.
Permit Information
Permit NumberFIR17-00336
StatusFinaled
Name SHILO AUTOMATIC SPRINKLER CO
Site Address 101 S CAPITOL BLVD Unit: 10TH FLR
Project NameUS Bank 10th FL Lobby Remodel
Customer Number 
ePlanReviewYes
Description
[US Bank 10th floor Lobby Remodel] - Quick Permit
Relocate and replace with new 10 pendent heads to accommodate the new lobby remodel.

[BLD17-00970] - This building is fire sprinklered because it is a high-rise. Permit is to remodel an existing 1,288 lobby area, lobby restroom and tenant space wall demo on the 10th and 11th floor of an existing high-rise building. This permit is approved contingent upon adhering to the approved plans on file. Work to include: removal of select interior nonbearing walls within the tenant space floor area, removal of select door/door frames, remove and replace select light fixtures, remove and replace restroom counter tops and mirrors, adding vertical grab bars in accessible toilet compartments?, removal of lobby soffit, construction of select interior non-bearing walls at corridor, new door/door frames, new lobby arched gypsum soffit ceiling, electrical work and interior finishes in compliance with chapter 8 of the 2012 IBC. This building is fully fire sprinklered any alterations or modifications to the buildings Fire Sprinkler or Fire Alarm system WILL REQUIRE A SEPARATE PERMIT and shall be installed per NFPA 13 & NFPA 72 as regulated by the Boise Fire Department. Note: No Occupancy allowed under this permit for the tenant space area. Tenant shall apply for certificate of occupancy prior to occupying tenant space. **JG**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection11/6/201711/6/201711/6/2017PPASS
DetailsJim Page
Final fire sprinkler inspection for area of work passed/complete.
INSP-Sprinkler Rough-in11/6/201711/6/201711/6/2017PPASS
DetailsJim Page
Rough to cover inspection for area of work complete, area of work approved for cover.
INSP-Final Inspection11/2/201711/3/201711/3/2017AFAIL
DetailsTroy Cobbley
Called contact and left message on voice mail. Went to job and did not make contact. I noted that final inspections are scheduled but no rough-in inspection has been performed. Ceilings will need to be removed for verification of hangers and piping.

Mike Martin is requesting a final inspection for the 10th floor elevator lobby of US Bank. Thank you. Phone #: ###-#### Inspection requested via web by Stan Beus