INSP-Final Inspection | 7/12/2018 | 7/13/2018 | 7/13/2018 | P | PASS |
Troy Cobbley
|
|
|
permit finaled
. forward flush passed
Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Final Inspection | 7/11/2018 | 7/12/2018 | 7/12/2018 | P | FAIL |
Troy Cobbley
|
|
|
Ceiling tile not installed yet. Interconnect with the fire alarm system was incorrect. Need forward flush test.
|
INSP-Sprinkler Rough-in | 6/26/2018 | 6/27/2018 | 6/27/2018 | P | PASS |
Troy Cobbley
|
|
|
Corrections made. Piping can be covered. Overhead hydro passed. FDC will need to be relocated/made accessible for fire dept personnel.
Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in/Hydro | 6/27/2018 | 6/27/2018 | 6/27/2018 | P | PASS |
Troy Cobbley
|
|
|
Corrections made. Piping can be covered. Overhead hydro passed. FDC will need to be relocated/made accessible for fire dept personnel.
Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 6/25/2018 | 6/26/2018 | 6/26/2018 | A | PART |
Troy Cobbley
|
|
|
Rough-in passed/piping can be covered. See the city approved plans for locations where several uprights need to be added and a large corridoe that the three pendant heads are overs paced
Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 5/11/2018 | 5/14/2018 | 5/14/2018 | P | PART |
Jim Page
|
|
|
Rough to cover inspection for overhead fire sprinkler piping located above hardlids in the southwest restrooms and corridor complete, approved for cover.
Mike Martin is the contact for this rough to cover inspection. He is hoping for an appointment in the PM. Thank you for your help. Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 2/14/2018 | 2/14/2018 | 2/14/2018 | P | PART |
Troy Cobbley
|
|
|
Rough-in for the overhead piping passed. Still missing acouple of earthquake braces that will be checked later. will need another cover inspection when the pendant drops have been installed. Per the contractor the architectural features in the main hallway will not have ceilings installed so it will allow the water from the upright sprinklers to provide protection.
Mike Martin is the contact for this inspection. Thank you. Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 2/12/2018 | 2/12/2018 | 2/12/2018 | P | PASS |
Troy Cobbley
|
|
|
Underground hydro test passed. Undergrond flush passed. I performed a walk through for a rough-in but not quite ready yet.
|
INSP-Sprinkler Rough-in | 8/22/2017 | 8/22/2017 | 8/22/2017 | P | PASS |
Troy Cobbley
|
|
|
Underground rough to cover passed. Piping can be buried.
|