INSP-Final Inspection | 5/1/2018 | 5/2/2018 | 5/2/2018 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Sprinkler Rough-in/Hydro | 3/14/2018 | 3/14/2018 | 3/14/2018 | P | PASS |
Troy Cobbley
|
|
|
Overhead hydro test passed
|
INSP-Supply line flush | 2/13/2018 | 2/14/2018 | 2/14/2018 | P | DONE |
Jim Page
|
|
|
Undergorund main line flush complete.
|
INSP-Sprinkler Rough-in | 1/25/2018 | 1/26/2018 | 1/26/2018 | A | PASS |
Jim Page
|
|
|
Rough to cover inspection for overhead fire sprinkler piping/tenting complete, approved for cover.
|
INSP-Sprinkler Rough-in | 1/25/2018 | 1/25/2018 | 1/25/2018 | P | CANC |
Jim Page
|
|
|
Rescheduled for 8AM 26JAN2018, this request is cancelled.
|
INSP-Sprinkler Rough-in | 12/7/2017 | 12/8/2017 | 12/8/2017 | P | PASS |
Jim Page
|
|
|
Rough to cover inspection for underground supply complete, approved for cover.
|