INSP-Final Inspection | 12/14/2017 | 12/14/2017 | 12/14/2017 | P | PASS |
Jim Page
|
|
|
Final inspection for underground supply complete.
|
INSP-Final Inspection | 12/11/2017 | 12/12/2017 | 12/12/2017 | A | PART |
Jim Page
|
|
|
Partial final inspection complete for overhead fire sprinklers, fire alarms/monitoring is still being worked on, when fire alarms are completed then fire sprinkler permit can be finaled.
|
INSP-Sprinkler Rough-in/Hydro | 12/11/2017 | 12/12/2017 | 12/11/2017 | A | DONE |
Jim Page
|
|
|
Overhead hydrostatic test witnessed, no pressure loss observed at gauge.
|
INSP-Supply line flush | 11/28/2017 | 11/29/2017 | 11/29/2017 | A | DONE |
Jim Page
|
|
|
Underground flush complete
|
INSP-Supply line flush | 11/27/2017 | 11/28/2017 | 11/28/2017 | P | CANC |
Jim Page
|
|
|
Flush rescheduled for 29NOV2017, this request is cancelled.
|
INSP-Sprinkler Rough-in/Hydro | 11/27/2017 | 11/28/2017 | 11/28/2017 | P | CANC |
Jim Page
|
|
|
Hydrostatic test cancelled per conversation with point of contact, Jim Baker Phone #: ###-#### , hydrostatic test will be rescheduled for a later date.
|
INSP-Sprinkler Rough-in | 10/18/2017 | 10/19/2017 | 10/19/2017 | A | PASS |
Jim Page
|
|
|
Rough to cover inspection for remaining underground supply complete, approved for cover.
|
INSP-Sprinkler Rough-in | 8/31/2017 | 8/31/2017 | 8/31/2017 | P | PART |
Jim Page
|
|
|
Rough to cover inspection for in building riser and stub out from the footing complete, area inspected approved for cover. Remaining underground to be installed at a later date.
|