INSP-Final Inspection | 6/25/2018 | 6/26/2018 | 6/26/2018 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled
Phone #: ###-#### Inspection requested via web by Matthew Lewis
|
INSP-Final Inspection | 6/14/2018 | 6/15/2018 | 6/15/2018 | A | FAIL |
Troy Cobbley
|
|
|
The interconnect with the fire alarm system passed. Permit can be finaled when the Smoking Canopy is done.
Phone #: ###-#### Inspection requested via web by Matthew Lewis
|
INSP-Final Inspection | 6/13/2018 | 6/14/2018 | 6/14/2018 | A | FAIL |
Troy Cobbley
|
|
|
Waiting on the project related fire alarm permit so that the interconnections can be tested. Forward flush passed. Need to inspect the Smokers Canopy.
Phone #: ###-#### Inspection requested via web by Matthew Lewis
|
INSP-Final Inspection | 6/12/2018 | 6/13/2018 | 6/13/2018 | A | CANC |
Troy Cobbley
|
|
|
Phone #: ###-#### Inspection requested via web by Matthew Lewis
|
INSP-Sprinkler Rough-in/Hydro | 6/11/2018 | 6/12/2018 | 6/12/2018 | A | PASS |
Troy Cobbley
|
|
|
24 hour air test on the dry system passed.
Phone #: ###-#### Inspection requested via web by Matthew Lewis
|
INSP-Sprinkler Rough-in/Hydro | 6/7/2018 | 6/7/2018 | 6/7/2018 | P | PART |
Troy Cobbley
|
|
|
The 200lb hydro test for the dry system and the wet stand pipe passed. The hydro tests for the 2nd, 3rd and 4th floors failed due to visible pressure loss on the guages.
Wet and Dry hydro Phone #: ###-#### Inspection requested via web by Matthew Lewis
|
INSP-Sprinkler Rough-in/Hydro | 6/5/2018 | 6/6/2018 | 6/6/2018 | A | CANC |
Troy Cobbley
|
|
|
Scheduled for the wrong day.
2hr and a 24hr Phone #: ###-#### Inspection requested via web by Matthew Lewis
|
INSP-Sprinkler Rough-in | 6/4/2018 | 6/5/2018 | 6/5/2018 | A | PASS |
Troy Cobbley
|
|
|
The remaining first floor piping is ok for cover. The previous corrections noted have been corrected.
hallways and rooms with grid Phone #: ###-#### Inspection requested via web by Matthew Lewis
|
INSP-Sprinkler Rough-in | 5/31/2018 | 6/1/2018 | 6/1/2018 | A | PART |
Troy Cobbley
|
|
|
first floor hallway and rooms with grid are ok for cover. I noted that a pendant will need to be added in a closet as discussed and two heads are overspaced in the corridor. I will check these at the next inspection.
|
INSP-Sprinkler Rough-in | 5/14/2018 | 5/15/2018 | 5/15/2018 | P | PART |
Jim Page
|
|
|
Rough to cover inspection for overhead fire sprinkler piping above ceiling grid in corridors on levels 2, 3 and 4 complete, approved for cover.
rough to cover hallways on 4th,3rd, and 2nd Phone #: ###-#### Inspection requested via web by Matthew Lewis
|
INSP-Sprinkler Rough-in | 5/10/2018 | 5/11/2018 | 5/11/2018 | P | PASS |
Troy Cobbley
|
|
|
See the city approved plans for location marked "ok" where piping is approved for cover. Todays area was the Laundry room.
partial rough in on first floor. Phone #: ###-#### Inspection requested via web by Matthew Lewis
|
INSP-Sprinkler Rough-in | 5/4/2018 | 5/7/2018 | 5/7/2018 | P | PASS |
Troy Cobbley
|
|
|
dining area and high part of lobby is ok for cover. See the city approved plans for notations with todays date.
|
INSP-Conference | 4/27/2018 | 4/30/2018 | 4/30/2018 | P | DONE |
Troy Cobbley
|
|
|
I met with Randy on the exterior canopy on the southeast corner of the building. There are issues getting the required sprinkler coverage under the canopy. I deferred him to my supervisors. Tim has already addressed the subject with the sprinkler designer.
Phone #: ###-#### Inspection requested via web by Matthew Lewis
|
INSP-Sprinkler Rough-in | 4/30/2018 | 4/30/2018 | 4/30/2018 | P | PART |
Troy Cobbley
|
|
|
the first floor soffit in the lobby is ok to cover. See the city approved plans for specific location
|
INSP-Sprinkler Rough-in | 4/10/2018 | 4/13/2018 | 4/13/2018 | A | PART |
Jim Page
|
|
|
Rough to cover inspection for level 1 fire sprinkler piping above sheetrock including dry system for drive through canopy complete, areas where ceiling grid will be installed will need a RTC inspection before covered, overehad fire sprinkler piping located above hardlids on level 1 inluding drive trhough canopy approved for cover.
|
INSP-Sprinkler Rough-in | 4/10/2018 | 4/12/2018 | 4/10/2018 | A | CANC |
Troy Cobbley
|
|
|
First floor Phone #: ###-#### >> Inspection requested via web by Matthew Lewis Inspection cancelled from web by: Matthew Lewis
|
INSP-Sprinkler Rough-in | 2/21/2018 | 2/22/2018 | 2/22/2018 | A | PASS |
Troy Cobbley
|
|
|
2nd, 3rd and 4th floor main piping, hangers and earthquake bracing inspected and approved. A separate cover inspection will be needed once the drops are cut.
Phone #: ###-#### Inspection requested via web by Matthew Lewis
|
INSP-Sprinkler Rough-in | 2/16/2018 | 2/20/2018 | 2/20/2018 | A | FAIL |
Troy Cobbley
|
|
|
There were no city approved plans on site to verify the earthquake bracing. I noted that the earthquake attachments for the cpvc piping are not shown on the plans.
hallways on 4th,3rd and 2nd Phone #: ###-#### Inspection requested via web by Matthew Lewis
|
INSP-Sprinkler Rough-in | 1/22/2018 | 1/22/2018 | 1/22/2018 | P | PASS |
Scott Arellano
|
|
|
Tenting inspection approved in all rooms and west corridor.
|
INSP-Sprinkler Rough-in | 1/19/2018 | 1/19/2018 | 1/19/2018 | P | FAIL |
Troy Cobbley
|
|
|
Todays inspection was for the fourth floor east of grid line 10. Piping in the rooms can not be covered due to tenting that needs repaired.
|
INSP-Sprinkler Rough-in | 1/18/2018 | 1/18/2018 | 1/18/2018 | P | PART |
Troy Cobbley
|
|
|
The rough-in and tenting has passed for the fourth floor piping guest rooms from column line 10 to the west end of the building. This piping can be covered.
|
INSP-Sprinkler Rough-in | 1/15/2018 | 1/16/2018 | 1/16/2018 | A | FAIL |
Troy Cobbley
|
|
|
Inspection was for the 4th floor wet and dry system. For cover approval of the wet system I need tenting done and all drops sidewalls installed (need approval for exposed cpvc piping in chases). For cover approval of the dry system I need resubmittals due to additional fittings and pipe routing, need data sheet for the Concealed Space Heads because they may be mounted too low, need the longitudinal bracing installed as discussed.
Phone #: ###-#### Inspection requested via web by Matthew Lewis
|
INSP-Sprinkler Rough-in | 12/26/2017 | 12/26/2017 | 12/26/2017 | P | PART |
Jim Page
|
|
|
Rough to cover inspection for overhead fire sprinkler piping/pendant heads located on levels 2 and 3 excluding the corridors complete, approved for cover.
|
INSP-Sprinkler Rough-in | 11/7/2017 | 11/8/2017 | 11/8/2017 | A | PASS |
Troy Cobbley
|
|
|
Partial first floor rooms rough-in passed. See the city approved plans for branchlines marked "ok" at the ends that have been inspected. These lines can be covered. The mains down the corridor has not been installed
Phone #: ###-#### Inspection requested via web by Matthew Lewis
|
INSP-Supply line flush | 11/7/2017 | 11/8/2017 | 11/8/2017 | A | CANC |
Troy Cobbley
|
|
|
Wrong permit number scheduled
|
INSP-Supply line flush | 11/7/2017 | 11/7/2017 | 11/7/2017 | P | CANC |
Troy Cobbley
|
|
|
Phone #: ###-#### >> Inspection requested via web by Matthew Lewis Inspection cancelled from web by: Matthew Lewis
|