INSP-Final Inspection | 2/27/2018 | 3/1/2018 | 3/1/2018 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled, Forward flush passed
|
INSP-Supply line flush | 2/27/2018 | 2/28/2018 | 2/27/2018 | P | CANC |
Katie Marron
|
|
|
Jeff from eagle water said he can be on site at 1:30 Phone #: ###-#### >> Inspection requested via web by Matthew Lewis Inspection cancelled from web by: Matthew Lewis
|
INSP-Final Inspection | 2/27/2018 | 2/27/2018 | 2/27/2018 | P | FAIL |
Troy Cobbley
|
|
|
Need the head guards installed and the coverage modified under the exterior canopy and the interconnection with the fire alarm panel tested..
Call prior to going Phone #: 20887175 >> Inspection requested via mobile web by Mike
|
INSP-Final Inspection | 2/27/2018 | 2/28/2018 | 2/27/2018 | P | CANC |
Katie Marron
|
|
|
Phone #: ###-#### >> Inspection requested via web by Matthew Lewis Inspection cancelled from web by: Matthew Lewis
|
INSP-Final Inspection | 2/22/2018 | 2/23/2018 | 2/23/2018 | A | FAIL |
Jim Page
|
|
|
Upright heads in main level 1 hallway are to close to the deck, a minimum of 1 in is required. Provide fire sprinkler head on northside of commercial kitchen hood. Dry sidewalls on exterior canopy need to be relocated to provide proper coverage. Utility room next to kitchen has head to far off of wall, room is ordinary hazard and sprinkler head is to far off of wall. Provide heads gaurds on fire sprinkler heads located under stairs and stair landing on level 1.
|
INSP-Sprinkler Rough-in/Hydro | 2/22/2018 | 2/23/2018 | 2/23/2018 | A | DONE |
Jim Page
|
|
|
Hydrostatic test for overhead fire sprinkler piping witnessed, no pressure loss observed at riser provided gauge (Underground was not fushed by end of inspection, system was filled with hose from domestic water supply, overhead cannot be turned on until flush is complete, if overhead is turned on before flush then all sprinkler heads will be pulled and drained due to possible debris)
|
INSP-Sprinkler Rough-in | 12/27/2017 | 12/28/2017 | 12/28/2017 | A | PASS |
Jim Page
|
|
|
Rough to cover inspection for overhead fire sprinkler piping complete, approved for cover.
|
INSP-Sprinkler Rough-in | 12/26/2017 | 12/26/2017 | 12/26/2017 | P | FAIL |
Jim Page
|
|
|
Provide fire sprinklers/piping for pendants in main lobby and area behind main lobby. Provide fire sprinkler next to commercial hood. Remove insulation that is caught on multiple heads in attic space.
|
INSP-Sprinkler Rough-in | 11/28/2017 | 11/29/2017 | 11/29/2017 | A | PART |
Jim Page
|
|
|
Partial rough to cover inspection complete for overhead fire sprinlkler piping, notated the city approved drawings areas approved for cover.
|
INSP-Sprinkler Rough-in/Hydro | 11/27/2017 | 11/28/2017 | 11/28/2017 | A | FAIL |
Troy Cobbley
|
|
|
No city approved plans or small documents on site. No inspection performed.
is only a partial inspection Phone #: ###-#### Inspection requested via web by Matthew Lewis
|