INSP-Final Inspection | 5/13/2019 | 5/15/2019 | 5/15/2019 | P | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection complete.
Austin Farnworth is the contact. This final is for the Liquor Store at Northgate Shopping Center. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Final Inspection | 5/8/2019 | 5/10/2019 | 5/10/2019 | A | FAIL |
Troy Cobbley
|
|
|
The fire alarm contractor is not ready with the final fire alarm panel/srpinkler system. However the fire alarm work in the Day Care, Empty Tenant and Goodwill is complete. The correction required for the FDC to supply both the wet and dry systems has been completed.
Jon Beazer is the contact. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 4/30/2019 | 5/2/2019 | 5/2/2019 | A | PASS |
Troy Cobbley
|
|
|
24 hour air test witnessed with no visible loss on the guage.
|
INSP-Sprinkler Rough-in | 4/30/2019 | 5/1/2019 | 5/1/2019 | A | DONE |
Troy Cobbley
|
|
|
24 hour air test started at 9:30 with 49psi on the guage.
Jon Beazer is the contact. This is for a 24 hour air test (part 1), to be preformed in the vacant space next to Rite Aid in the back. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Conference | 4/15/2019 | 4/15/2019 | 4/15/2019 | P | DONE |
Jim Page
|
|
|
Fire conference complete, FDC bells will need to be installed in discussed locations. FDC by Goodwill appears to supply only the wet system, FDC will need to be configured to supply both wet and dry systems without using the wet system as the FDC feed to the dry system.
Jon Beazor is the contact. This is to be a consultation about fire alarms and alarm bells. The contact requests that you give him an approximate time that you''ll be able to meet for the consultation so he can have the general contractor meet there as well. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in/Hydro | 4/10/2019 | 4/11/2019 | 4/11/2019 | P | DONE |
Jim Page
|
|
|
Hydrostatic test for overhead fire sprinkler on Rite Aid dry system witnessed, no pressure loss observed.
Jon Beazer is the contact. This is for a Hydro only. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 4/8/2019 | 4/9/2019 | 4/9/2019 | P | FAIL |
Jim Page
|
|
|
Rite Aid dry system lost 11 PSI during 24 hour air test.
The contact is Jon Beazor. This is for the 2nd part of the 24 hour air test. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 4/5/2019 | 4/8/2019 | 4/8/2019 | P | PART |
Jim Page
|
|
|
24 hour ir test atarted at 1PM at 45 PSI.
Jon Beazer is the contact. This is actually for a 24 hour air test. Contact Beazer for questions. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Final Inspection | 3/28/2019 | 3/29/2019 | 3/29/2019 | A | FAIL |
Jim Page
|
|
|
Alarm pressure switch on both east and west dry systems not hooked up to FDC bell, valve labeling on alarm side does match valve configuration.
Gabe Garduno is the contact. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Final Inspection | 3/26/2019 | 3/27/2019 | 3/27/2019 | A | FAIL |
Jim Page
|
|
|
Provide restricted orifice at inspectors test. Two dry pendant heads will need to be re-measured and replaced, escutcheon cannot be installed, head is to short. Contractor needs to verify which anti-freeze loops will stay active and which ones will be removed, if anti-freeze loop is abondoned then piping needs to meet requirements in NFPA 13, Chapter 27.
Gabe Garduno is the contact. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Final Inspection | 3/21/2019 | 3/22/2019 | 3/22/2019 | P | CANC |
Jim Page
|
|
|
Cancelled per conversation with POC, will be rescheduled for a later date.
Gabe Garduno is the contact. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Final Inspection | 3/14/2019 | 3/15/2019 | 3/15/2019 | A | CANC |
Jim Page
|
|
|
Will be rescheduled to coincide with fire alarm inspection, this request is cancelled.
The contact is Jeff Chaney. He requests that he be notified ahead of time when the inspector will be there. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Final Inspection | 3/11/2019 | 3/12/2019 | 3/12/2019 | P | FAIL |
Jim Page
|
|
|
Air compressor is not hard-wired in and is not on a dedicated circuit. Dry system needs to have a listed air maintenance device per 2016 NFPA 13, section 7.2.6.6.
Jeff Chaney is the contact for this final inspection. Thank you for your help. Have a nice day. Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 1/14/2019 | 1/15/2019 | 1/15/2019 | P | PASS |
Jim Page
|
|
|
Rough to cover inspection for dry system in new canopy complete, approved for cover.
Gabe is the contact Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 12/18/2018 | 12/18/2018 | 12/18/2018 | P | PASS |
Jim Page
|
|
|
Rough to cover inspection for remaining sprinkler piping in Rite Aid canopy complete, approved for cover.
Jeff Chaney is the contact for this RTC inspection. Thank you for your help and have a nice day. Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 12/6/2018 | 12/7/2018 | 12/7/2018 | A | PART |
Jim Page
|
|
|
Rough to cover inspection for overhead fire sprinkler piping in attic spaces on the east and west of high roof section on Rite Aid complete, approved for cover.
Jeff Chaney is the contact. Thank you for your help! Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 10/17/2018 | 10/18/2018 | 10/18/2018 | A | FAIL |
Jim Page
|
|
|
All combustible materials in over-builds and concealed spaces requires fire sprinkler coverage per NFPA13, fire sprinklers will required in un-protected areas as discussed, if areas discussed are left un-protected then inspection requests for this project will result ikn a failure.
Mike Bierman is the contact for this RTC inspection. Thank you for your help. Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 10/16/2018 | 10/17/2018 | 10/17/2018 | A | DONE |
Jim Page
|
|
|
24 hour test complete on 4 new dry systems.
Jeff is requesting a 24 hr. air test. Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in/Hydro | 8/22/2018 | 8/23/2018 | 8/23/2018 | P | DONE |
Jim Page
|
|
|
Hydrostatic test for overhead fire sprinkler on new dry systems witnessed, no pressure loss observed at riser provided gauges.
Jim Baker is the contact for this 4 overhead hydro. It is on 4 different risers. He is hoping for an appointment in the late AM or early PM. We appreciate your help. Thank you. Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 6/20/2018 | 6/21/2018 | 6/21/2018 | A | PASS |
Jim Page
|
|
|
Rough to cover inspection for overhead fire sprinkler piping in the Goodwill section complete, approved for cover.
Jeff Chaney is the contact for this inspection. Thank you for your help. Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 6/4/2018 | 6/5/2018 | 6/5/2018 | P | PART |
Jim Page
|
|
|
Rough to cover inspection for overhead fire sprinkler piping west of theater entrance and east of Goodwill complete, approved for cover.
Jeff Chaney is the contact for this overhead rough-in. Thank you. Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 5/1/2018 | 5/2/2018 | 5/2/2018 | P | PART |
Jim Page
|
|
|
Rough to cover inspection for overhead fire sprinkler piping east of "The Barley Pub" tenant space complete, approved for cover.
|
INSP-Sprinkler Rough-in | 4/5/2018 | 4/5/2018 | 4/5/2018 | P | PART |
Jim Page
|
|
|
Rough to cover inspection for remaining pipe on system 2 complete, approved for cover.
|
INSP-Sprinkler Rough-in | 3/15/2018 | 3/16/2018 | 3/16/2018 | P | PART |
Jim Page
|
|
|
Rough to cover inspection for west side of system 2 complete, west side of system 2 approved for cover.
|
INSP-Sprinkler Rough-in | 3/13/2018 | 3/14/2018 | 3/14/2018 | A | PART |
Jim Page
|
|
|
Rough to cover inspection complete for west building to include connection between middle and west building, approved for cover.
|
INSP-Sprinkler Rough-in | 3/8/2018 | 3/12/2018 | 3/12/2018 | P | PART |
Jim Page
|
|
|
Partial rough to cover inspection complete, southeast area canopy of west building approved for cover.
|
INSP-Sprinkler Rough-in | 3/8/2018 | 3/9/2018 | 3/9/2018 | P | PART |
Troy Cobbley
|
|
|
The only additional canopy that can have the piping covered in the west most/end of system . This canopy is in the walkway between the buildings. The other areas have issues with missing upright coverage and pendants and uprights not being installed as per plan.
Todd Ketterling is the contact for this inspection. Thank you. Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 3/8/2018 | 3/9/2018 | 3/8/2018 | P | CANC |
Jim Page
|
|
|
Todd Ketterling is the contact for this inspection. Thank you. Phone #: ###-#### >> Inspection requested via web by Stan Beus Inspection cancelled from web by: Stan Beus
|
INSP-Sprinkler Rough-in | 2/13/2018 | 2/14/2018 | 2/14/2018 | A | PART |
Jim Page
|
|
|
Partial rough to cover inspection for scope of work complete, west building inspected and approved for cover. FDC will need to be relocated due to access issues from daycare on northside of building.
|