INSP-Final Inspection | 10/30/2018 | 10/30/2018 | 10/30/2018 | A | PASS |
Jim Page
|
|
|
Final inspection for underground supply complete.
|
INSP-Sprinkler Rough-in/Hydro | 9/6/2018 | 9/7/2018 | 9/7/2018 | A | DONE |
Jim Page
|
|
|
Hydrostatic test for undergorund supply witnessed, no pressure loss observed at contractor provided gauge.
Phone #: ###-#### Inspection requested via web by Matthew Lewis
|
INSP-Supply line flush | 9/6/2018 | 9/6/2018 | 9/6/2018 | P | DONE |
Jim Page
|
|
|
Underground supply flush complete.
Phone #: ###-#### Inspection requested via web by Matthew Lewis
|
INSP-Sprinkler Rough-in/Hydro | 12/4/2017 | 12/4/2017 | 12/4/2017 | P | PASS |
Jim Page
|
|
|
Rough to cover inspection for underground supply complete, underground supply approved for cover.
|