Permit Information
Permit NumberFIR17-00682
StatusFinaled
Name TREASURE VALLEY FIRE PROTECTION
Site Address 222 N 8TH ST
Project NameDIABLO & SONS T.I.
Customer Number 
ePlanReviewYes
Description
[Diablo & Sons TI.]
The fire sprinkler scope of work consists of basement only. Demo existing piping and add a new secondary main and branch lines to the new wall and ceiling layout.

[BLD17-02185]
The fire sprinkler system is used to substitute for 1-hr fire-resistance-rated construction of the building. To remodel a 2,289 square foot restaurant tenant space located on the 1st story and to expand the sidewalk seating to about 952 total square feet. The entry to the adjacent East tenant space will also be remodeled to include an entry vestibule at the exterior door. In addition, the windows of the East tenant space will be replaced with glazed vertical sliding overhead exterior doors. Work is to include interior nonbearing walls, suspended ceilings, gypsum board ceilings, sound attenuation insulation and plywood ceiling, three entry vestibules at exterior doors, maintaining an existing Type I grease hood and duct system with a listed 1-hr duct wrap system installed from the hood all the way to the exhaust fan on the roof, a modified hood make-up air system, a new Type I grease hood and duct system for solid fuel burning cooking equipment with a listed 1-hr duct wrap system installed from the hood all the way to the exhaust fan on the roof and served by the modified make-up air system, kitchen equipment, glazed vertical sliding overhead exterior doors, exterior doors, millwork, and finishes. To remodel food preparation areas in the basement (total area of about 3,000 square feet). Work is to include interior nonbearing walls, a bearing wall with a concrete footing, a new concrete floor on steel decking to replace a section of wood floor above the new grease hoods, two Type I grease hoods each served by a grease duct that becomes a common grease duct system with make-up air, a listed 1-hr grease duct wrap system continuous from the grease hoods all the way to the exhaust fan on the roof, walk-in coolers, food preparation equipment, and finishes. The changes to the roof structure required to support the added roof top equipment, improved roof access to serve new and existing roof top equipment, the chase wall through the 2nd story to accommodate ducts, and the increased exit access headroom height in the basement were all done under separate permits. The work is required to comply with the approved drawings, with the plan review report, and with all applicable codes and ordinances. The fire sprinkler system is required to comply with NFPA 13 and the fire alarm system is required to comply with NFPA 72 as regulated by the Fire Department. Separate fire sprinkler permits and fire alarm permits shall be obtained prior to beginning any modification or installation work on such systems. **CJW**

Alternative Materials and Methods:
This project includes approved code alternates to the following fire protection systems and/or building life safety systems. Please review the supplemental documents attached to this building permit case for details. Fire protection “shop drawings” shall include approved code alternate design.

• There is one AMM at this time. The AMM does not pertain to the fire protection.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection7/27/20187/30/20187/30/2018APASS
DetailsJim Page
Final fire sprinkler inspection for area of work complete.

Please call Tom with time frame. Phone #: ###-#### Inspection requested via web by Jeff Packham
INSP-Sprinkler Rough-in4/17/20184/18/20184/18/2018APART
DetailsJim Page
Rough to cover inspection for overhead fire sprinkler piping located above new cooler in basement level complete, piping that is above cooler approved for cover.
INSP-Sprinkler Rough-in12/19/201712/19/201712/19/2017PPART
DetailsJim Page
Fire sprinkler inspection for TCO requested area in the basement (Prep kitchen, coolers and corridor) complete.
INSP-Sprinkler Rough-in12/13/201712/14/201712/14/2017APART
DetailsJim Page
Fire sprinkler work for food prep area complete (part of the TCO requested area) Fire sprinklers will need to be added to the area for the path of egress, issue has been discussed with job superintendant.
INSP-Sprinkler Rough-in11/30/201711/30/201711/30/2017APASS
DetailsTroy Cobbley
See the city approved plans for location with todays date where piping is ok to cover.