Information based on query as of Friday, June 28, 2024.
Permit Information
Permit NumberFIR17-00695
StatusFinaled
Name SHILO AUTOMATIC SPRINKLER CO
Site Address 101 S CAPITOL BLVD Unit: 8TH FLR
Project NamePCA TI @ US Bank 8th Floor
Customer Number 
ePlanReviewYes
Description
[PCA TI - US Bank Building - 8th Floor] - Quick Permit
Relocate/replace with new, and add new pendents to accommodate the new wall and ceiling layout for the PCA TI on the 8th Floor of the US Bank Building.

[BLD17-02187]
This building is sprinklered to comply with high-rise requirements. Permit for tenant improvement design for PCA in the US Bank Building on the entire 8th floor 14,600 sq ft. Scope of work to include interior nonbearing demolition and framing of new floor plan per approved drawings. New mechanical, electrical and plumbing shall be permitted separately. This building is fully Fire Sprinklered with an approved Fire Alarm system. Any alterations or modifications to the buildings Fire Sprinkler or Fire Alarm system WILL REQUIRE A SEPARATE PERMIT and shall be installed per NFPA 13 & NFPA 72 as regulated by the Boise Fire Department. **ajs**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection12/27/201712/28/201712/28/2017PPASS
DetailsJim Page
Final fire sprinkler inspection for area of work complete.
INSP-Final Inspection12/18/201712/19/201712/19/2017AFAIL
DetailsJim Page
Fire sprinkler heads overspaced.
INSP-Sprinkler Rough-in12/15/201712/15/201712/15/2017APASS
DetailsJim Page
Rough to cover inspection for overhead fire sprinkler piping in area of work complete, approved for cover.