INSP-Final Inspection | 2/21/2018 | 2/26/2018 | 2/26/2018 | A | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection for area of work complete.
|
INSP-Sprinkler Rough-in | 2/21/2018 | 2/26/2018 | 2/21/2018 | A | CANC |
Jim Page
|
|
|
Phone #: ###-#### >> Inspection requested via web by Matthew Lewis Inspection cancelled from web by: Matthew Lewis
|
INSP-Sprinkler Rough-in/Hydro | 2/13/2018 | 2/14/2018 | 2/14/2018 | A | PASS |
Jim Page
|
|
|
Rough to cover inspection for overhead fire sprinkler piping in area of work complete, approved for cover.
|
INSP-Sprinkler Rough-in/Hydro | 2/13/2018 | 2/13/2018 | 2/13/2018 | P | CANC |
Jim Page
|
|
|
Inspection request was for 14FEB2018, this request is cancelled per point of contact, Steve phone# ###-####
|
INSP-Sprinkler Rough-in/Hydro | 2/13/2018 | 2/14/2018 | 2/13/2018 | P | CANC |
Jim Page
|
|
|
Phone #: ###-#### >> Inspection requested via web by Matthew Lewis Inspection cancelled from web by: Matthew Lewis
|
INSP-Sprinkler Rough-in | 1/18/2018 | 1/19/2018 | 1/19/2018 | A | PART |
Scott Arellano
|
|
|
Ok to cover two heads in hard lid areas. Discussed surface mounted light placement relative to SSP location in utility closet. GC to install light away from SSP to avoid obstruction.
|