INSP-Final Inspection | 6/13/2018 | 6/14/2018 | 6/14/2018 | A | PASS |
Jim Page
|
|
|
Final fire sprinkler inspectin for area of work complete.
Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 5/15/2018 | 5/16/2018 | 5/16/2018 | A | PASS |
Jim Page
|
|
|
Rough to cover inspection for overhead fire sprinkler piping in area of work complete, approved for cover.
Jeff Chaney is the contact for this inspection. Thank you. Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 5/14/2018 | 5/15/2018 | 5/15/2018 | P | CANC |
Jim Page
|
|
|
Inspection rescheduled for 16MAY2018 due to inspection schedule load.
Jeff Chaney is the contact for this inspection. Thank you. Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 5/11/2018 | 5/14/2018 | 5/14/2018 | P | PART |
Jim Page
|
|
|
Partial rough to cover inspection complete for overhead fire sprinkler piping, remaining overhead fire sprinkler piping in area of work to be inspected at a later date.
Jeff Chaney is the contact for this rough to cover inspection. Thank you for your help. Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 5/8/2018 | 5/9/2018 | 5/9/2018 | P | CANC |
Jim Page
|
|
|
Not ready for inspection, inspection request will be rescheduled for a later date, this request is cancelled per conversation with point of contact.
Jeff Chaney is the contact for this rough to cover inspection. Thank you for your help. Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 3/26/2018 | 3/27/2018 | 3/27/2018 | P | PART |
Jim Page
|
|
|
Rough to cover inspection for overhead fire sprinkler piping located above hardlids complete, hardlids in area of work approved for cover.
|