Permit Information
Permit NumberFIR17-00773
StatusFinaled
Name STATEFIRE DC SPECIALTIES
Site Address 10539 W OVERLAND RD
Project NameTrade Viet Market
Customer Number 
ePlanReviewYes
Description
[Trade Viet Market] - Quick Permit
A new kitchen, prep area and 2 coolers are being added to an already sprinklered building. Relocate the existing pendents to center of tile in these new areas and add dry pendents to the cooler ares.

[BLD17-03830]
Permit is to remodel an existing 22,683 sq. ft. retail space in an existing building. Approval is contingent upon adhering to the approved plans on file. Work to include: removal of select interior nonbearing walls, removal of select door/door frames, removal of select interior storefront glazing, removal of select plumbing fixtures, removal of select acoustic ceiling, removal of select roof assembly for new mechanical rooftop curbs, construction of interior non-bearing walls to create a kitchen and prep areas, select ne door/door frames, select new acoustic ceiling, relocate light fixtures, millwork, (2) walk-in coolers, (2) type 1 hoods, (1) rooftop MAU, rooftop exhaust fans, concrete slab work for new underground plumbing, electrical work. Plumbing work, mechanical work and interior finishes in compliance with Ch. 8 of the 2012 IBC. This building is fully Fire Sprinklered. Any alterations or modifications to the buildings Fire Sprinkler or Fire Alarm system WILL REQUIRE A SEPARATE PERMIT and shall be installed per NFPA 13 & NFPA 72 as regulated by the Boise Fire Department. **JG**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection1/25/20181/26/20181/26/2018APASS
DetailsTroy Cobbley
Permit finaled


Phone #: ###-#### Inspection requested via web by Matthew Lewis
INSP-Sprinkler Rough-in1/18/20181/18/20181/18/2018PPART
DetailsTroy Cobbley
Rough-in passed. Piping can be covered. I noted that at the south end of the new coolers it appears the pendant heads will be overspaced off of the cooler walls. I also noted pendant heads overspaced out side of the scope of work near the south end of the tenant space.