INSP-Final Inspection | 7/25/2019 | 7/26/2019 | 7/26/2019 | A | PASS |
Jim Page
|
|
|
Previously noted items that were notated on the city approved drawings has been corrected, final fire sprinkler inspection for area of work complete.
Clarence Phone #: ###-####
|
INSP-Final Inspection | 6/25/2019 | 6/25/2019 | 6/25/2019 | P | FAIL |
Jim Page
|
|
|
Dillon has the city approved drawings that have been notated, numerous areas has no sway bracing, sway bracing is shown on the city approved drawings, sway bracing needs to be installed or removed from the city approved drawings. Numerous heads under duct work and piping has been added but the approved drawings do not reflect the install. City approved drawings have been notated where corrections need to be made.
Dillon Phone #: ###-####
|
INSP-Final Inspection | 6/18/2019 | 6/19/2019 | 6/19/2019 | A | CANC |
Jim Page
|
|
|
Inspection request cancelled per conversation with point of contact, city approved drawings/small documents could not be located, city approved drawings and small documents are required for inspection.
Dillion Phone #: ###-####
|
INSP-Final Inspection | 4/12/2019 | 4/12/2019 | 4/12/2019 | P | CANC |
Jim Page
|
|
|
Per conversation with my supervisor, Adele Schaffeld-Griffin, notes entered reading "Final fire sprinkler sign off of inspections for this permit will be completed at the same time as the life safety inspection is completed under the building permit." Please coordination with the general contractor to schedule the final inspections. Onsite inspection request for today will need to be rescheduled until coordinated inspections for the life safety can be scheduled.
Clarence Phone #: ###-####
|
INSP-Final Inspection | 7/30/2018 | 7/31/2018 | 7/31/2018 | P | PART |
Jim Page
|
|
|
Final fire sprinkler inspection complete, fire sprinkler permit will remain in issued status until project is complete due to possible obstructions needing coverage.
Chris Phone #: ###-####
|
INSP-Sprinkler Rough-in/Hydro | 6/15/2018 | 6/18/2018 | 6/18/2018 | P | DONE |
Jim Page
|
|
|
Hydrostatic test for overhead fire sprinkler piping witnessed, no pressure loss observed at riser provided gauge.
Chris Phone #: ###-####
|