INSP-Final Inspection | 10/19/2018 | 10/23/2018 | 10/23/2018 | A | PASS |
Troy Cobbley
|
|
|
permit finaled
|
INSP-Supply line flush | 7/23/2018 | 7/24/2018 | 7/24/2018 | A | PASS |
Troy Cobbley
|
|
|
Underground flush of the three supplies in the breeze way passed.
Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 7/23/2018 | 7/23/2018 | 7/23/2018 | P | FAIL |
Troy Cobbley
|
|
|
Shilo, again, scheduled the wrong permit. This underground permit is scheduled, for a rough-in and a overhead hydro. The correct permit to be scheduled should be for the overhead piping. I went to the project anyway and found un-insppected piping covered with insulation and the dry wall contractor covering sprinkler piping as I watched. I asked him to stop and he told me go talk to Pat. I stopped the inspection until all piping is exposed.
Hrdro above ground Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 7/16/2018 | 7/18/2018 | 7/18/2018 | P | CANC |
Troy Cobbley
|
|
|
Contractyor called wrong permit in for inspection. I left message on the contacts voice mail at 11:30 that I wopuld be there in half an hour but when I arrived no one was there. I placed another phone call and spoke to the contact and he stated that he did not possess the updated drawings and that he would reschedule for tomorrow morning.
Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 7/11/2018 | 7/16/2018 | 7/16/2018 | A | FAIL |
Troy Cobbley
|
|
|
As-builts need to be approved showing the pipe routing changes prior to a cover inspection being requested.
Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in/Hydro | 6/29/2018 | 6/29/2018 | 6/29/2018 | P | PASS |
Troy Cobbley
|
|
|
Underground hydro test passed
Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in/Hydro | 6/19/2018 | 6/20/2018 | 6/20/2018 | P | CANC |
Troy Cobbley
|
|
|
Phone #: ###-#### >> Inspection requested via web by Stan Beus Inspection cancelled from web by: Stan Beus
|
INSP-Supply line flush | 6/18/2018 | 6/19/2018 | 6/19/2018 | P | PASS |
Troy Cobbley
|
|
|
The supply line flush of the 4" passed. We did not flush the breeze way piping today.
Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Supply line flush | 6/15/2018 | 6/18/2018 | 6/18/2018 | P | CANC |
Troy Cobbley
|
|
|
Phone #: ###-#### >> Inspection requested via web by Stan Beus Inspection cancelled from web by: Stan Beus
|
INSP-Sprinkler Rough-in | 1/29/2018 | 1/30/2018 | 1/30/2018 | A | PASS |
Troy Cobbley
|
|
|
The underground supply piping is ok for cover.
|