INSP-Final Inspection | 1/17/2019 | 1/18/2019 | 1/18/2019 | A | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection complete.
George Jess is the contact for this final inspection. Thank you. Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in/Hydro | 1/8/2019 | 1/9/2019 | 1/9/2019 | P | DONE |
Jim Page
|
|
|
Hydrostatic test for overehad fire sprinkler piping witnessed, no pressure loss observed on both wet systems.
Overhead Hydro and the contact is George. Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in/Hydro | 1/7/2019 | 1/8/2019 | 1/8/2019 | A | CANC |
Jim Page
|
|
|
Cancelled per conversation woith point of contact.
200lb hydro. George is the contact. Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 1/7/2019 | 1/8/2019 | 1/8/2019 | A | PASS |
Jim Page
|
|
|
Rough to cover inspection for overhead fire sprinkler piping complete, approved for cover.
overhead RTC. Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 12/20/2018 | 12/21/2018 | 12/21/2018 | A | PART |
Jim Page
|
|
|
Rough to cover inspection for overhead fire sprinkler piping in kitchen complete, kitchen area approved for cover. Fire sprinkler heads around kitchen cooking hood will be changed to 200 degree heads before final inspection.
George is the contact. He asked for an inspection for a RTC in the Kitchen area. Thank you for your help! Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 12/11/2018 | 12/12/2018 | 12/12/2018 | A | PART |
Jim Page
|
|
|
Partial rough to cover inspection for overhead fire sprinkler piping on level 2 complete, notated city approved drawings with yellow highlighter/red ink areas inspected and approved for cover. Temporary FDC will be installed by fire sprinkler riser room due to access, permenant location currently has portable buildings that will be removed in the future so a temp FDC will be required for occupancy until permenant location can be accessed by fire truck.
George Jess is the contact for this rough to cover inspection on the 2nd floor. Thank you for your help. Have a nice day. Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 11/28/2018 | 11/29/2018 | 11/29/2018 | P | PART |
Jim Page
|
|
|
Partial rough to cover inspection for overhead fire sprinkler piping on level 2 complete, notated city approved drawings with pink highlighter/red ink areas inspected and approved for cover.
George Jess is the contact for this rough to cover inspection. He is hoping for an appointment in the PM. Thank you for your help. Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 11/1/2018 | 11/2/2018 | 11/2/2018 | A | PART |
Jim Page
|
|
|
Partial rough to cover inspection for overhead fire sprinkler piping complete, notated city approved drawings with pink highlighter/red ink areas approved for cover. Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 10/10/2018 | 10/11/2018 | 10/11/2018 | P | PART |
Jim Page
|
|
|
Notated city approved drawings with pink highlighter/red ink hardlids approved for cover.
Hard lid inspection Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 9/17/2018 | 9/18/2018 | 9/19/2018 | A | PASS |
Adele J Schaffeld-Griffin
|
|
|
Forrest inspection comments-Inspection for cover completed at first floor below stairs sheetrock ceilings (3 locations). Be aware of possible obstructions to coverage due to surface mounted light fixtures not yet installed. Hard lids need to be inspected only. Phone #: ###-#### >> Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 8/9/2018 | 8/10/2018 | 8/10/2018 | A | PART |
Jim Page
|
|
|
Rough to cover inspection for overhead fire sprinkler piping located above hardlids on level 1 complete, notated the city approved drawings with pink highlighter areas approved for cover.
George Jess is the contact for this inspection. He is request a Hard Lid inspection in the bathrooms. He is hoping for an appointment in the AM. We appreciate your help with this. Thank you. Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Supply line flush | 7/2/2018 | 7/3/2018 | 7/3/2018 | A | DONE |
Jim Page
|
|
|
Underground main line flush complete.
George Jess is the contact for this underground Hydro and Flush. An appointment has been scheduled with Jim Page for 10AM and with Gus with Suez. Thank you for your help. Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in/Hydro | 7/2/2018 | 7/3/2018 | 7/3/2018 | A | DONE |
Jim Page
|
|
|
Underground hydrostatic test witnessed, no pressure loss observed at contractor provided gauge.
George Jess is the contact for this Underground Hydro ; Flush. It has been discussed with Jim Page ; Gus with Suez. The appointment time is for 10AM., thank you for your help. Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Supply line flush | 6/29/2018 | 7/2/2018 | 7/2/2018 | A | CANC |
Jim Page
|
|
|
Inspection request cancelled per conversation with installing contractors office, request will be rescheduled for a later date.
George Jess is the contact for this underground flush and underground hydro inspection. We visited with Jim and scheduled an appointment for 10AM. Thank you for your help. Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in/Hydro | 6/29/2018 | 7/2/2018 | 7/2/2018 | A | CANC |
Jim Page
|
|
|
George Jess is the contact for this underground Hydro and Flush. We talked to Jim Page to schedule and coordinate with Stacey @ Suez. The appointment that was made was for 10 AM. Thank you for your help. Phone #: ###-#### >> Inspection requested via web by Stan Beus Inspection cancelled from web by: Stan Beus
|