INSP-Final Inspection | 10/28/2019 | 10/29/2019 | 10/29/2019 | P | PASS |
Jim Page
|
|
|
Final inspection for scope of work is complete.
We would like to discuss the final for this work. Please call Cameron with questions. Phone #: ###-#### Inspection requested via web by Jeff Packham
|
INSP-Sprinkler Rough-in/Hydro | 3/19/2018 | 3/19/2018 | 3/19/2018 | P | DONE |
Jim Page
|
|
|
Undergound supply hydrostatic test witnessed, no pressure loss observed at riser supplied gauge.
|
INSP-Supply line flush | 3/16/2018 | 3/19/2018 | 3/19/2018 | A | DONE |
Jim Page
|
|
|
Underground main line flush complete
|
INSP-Sprinkler Rough-in | 3/8/2018 | 3/9/2018 | 3/8/2018 | A | PASS |
Jim Page
|
|
|
Rough to cover inspection for remaining underground complete, approved for cover.
|
INSP-Sprinkler Rough-in | 1/31/2018 | 2/1/2018 | 2/1/2018 | A | PART |
Jim Page
|
|
|
Rough to cover inspection for installed underground piping complete, piping terminates about 10 feet from building. Piping installed is approved for cover.
|
INSP-Sprinkler Rough-in/Hydro | 1/30/2018 | 1/31/2018 | 1/30/2018 | A | CANC |
Jim Page
|
|
|
Fire Service Cover Inspection Phone #: ###-#### >> Inspection requested via web by Christophe Wilson Inspection cancelled from web by: Christophe Wilson
|